# 262101330676
Unscheduled inspection
Start date: 2021-11-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 262100551373
Unscheduled inspection
Start date: 2021-08-31, end date: —, duration: —
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection:
# 262100551154
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 262100550778
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: This check is carried out with the aim of: expiration of the deadlines for the execution of the previously issued prescription dated 03/29/2021 No. 23/01-2020;
The objectives of this audit are to prevent, identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out the construction.;
The subject of this review is:
- elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation (hereinafter referred to as violations) identified during construction control and the implementation of regional state construction supervision, as well as compliance with the prohibition to proceed with work until acts on the elimination of such violations are drawn up;
- compliance with the regulations of state control (supervision) bodies, municipal control bodies
# 262100343417
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: This check is carried out with the aim of: expiration of the deadlines for the execution of the previously issued prescription dated 03/29/2021 No. 23/01-2020;
The objectives of this audit are to prevent, identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out the construction.;
The subject of this review is:
- elimination of violations of compliance of completed works with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation (hereinafter referred to as violations) identified during construction control and the implementation of regional state construction supervision, as well as compliance with the prohibition to proceed with work until acts on the elimination of such violations are drawn up;
- compliance with the regulations of state control (supervision) bodies, municipal control bodies
# 262005168276
Unscheduled inspection
Start date: 2020-10-05, end date: 2020-10-31, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: Notification of completion of construction Final inspection the objectives of this inspection are to prevent identify and suppress violations of the law on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out construction, compliance with the procedure for conducting construction control, maintaining general and or special logs of work, executive documentation, and drawing up certificates of work inspection of structures, sections of engineering and technical support networks, and compliance with other requirements when performing works established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources, compliance with mandatory requirements and or requirements established by municipal legal acts
# 262005204329
Unscheduled inspection
Start date: 2020-10-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 262004288842
Unscheduled inspection
Start date: 2020-02-13, end date: 2020-03-12, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: notification of LLC "OMS" on the deadlines for the completion of works subject to inspection during the construction of a capital construction facility I Installation of an electric lighting line and completion of construction the objectives of this inspection are to prevent, identify and suppress violations of legislation on urban development by the developer, the technical customer, and the person carrying out construction, including technical regulations and design documentation, compliance with the construction control procedure, general and or special work logs of executive documentation, preparation of certificates of inspection of structures of sections of engineering and technical support networks, compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used, compliance with mandatory requirements and or requirements established by municipal legal acts