# 772101422082
Unscheduled inspection
Start date: 2021-12-06, end date: 2021-12-08, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772101288105
Unscheduled inspection
Start date: 2021-11-08, end date: 2021-11-19, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772101332663
Unscheduled inspection
Start date: 2021-11-15, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772101253349
Unscheduled inspection
Start date: 2021-10-25, end date: 2021-10-29, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100633946
Unscheduled inspection
Start date: 2021-09-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100611965
Unscheduled inspection
Start date: 2021-09-02, end date: 2021-09-03, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100333574
Unscheduled inspection
Start date: 2021-07-07, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100195902
Unscheduled inspection
Start date: 2021-05-13, end date: 2021-05-21, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100176958
Unscheduled inspection
Start date: 2021-04-27, end date: 2021-04-29, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100046659
Unscheduled inspection
Start date: 2021-03-10, end date: 2021-03-19, duration: 8
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the inspection program; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the instruction issued by Mosgosstroynadzor compliance of the work and the construction materials used in the construction, reconstruction process the capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772105304161
Unscheduled inspection
Start date: 2021-01-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005214329
Unscheduled inspection
Start date: 2020-11-09, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004451115
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803179099
Unscheduled inspection
Start date: 2018-07-11, end date: 2018-07-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803141454
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803067490
Unscheduled inspection
Start date: 2018-01-23, end date: 2018-02-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802821750
Unscheduled inspection
Start date: 2017-11-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802667919
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used