# 422005150662
Unscheduled inspection
Start date: 2020-09-30, end date: 2020-10-06, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation Tasks verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development
# 422100470011
Unscheduled inspection
Start date: 2021-08-18, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: cel proverki- sootvetstvie vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov i izdelii v processe stroitelstva obekta (montazh liftov, montazh oborudovaniya gazovoi kotelnoi), a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii (v tom chisle s uchetom izmenenii, vnesennyh v rabochuyu dokumentaciyu i yavlyayuschihsya v sootvetstvii s chastyu 1.3 stati 52 nastoyaschego Kodeksa chastyu takoi proektnoi dokumentacii);
zadacha proverki - soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva;
predmet proverki − soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti.
# 422100012070
Unscheduled inspection
Start date: 2021-02-17, end date: 2021-02-19, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of checking the compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work, with the requirements of design documentation and checking compliance with the requirements of Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the task and subject of this check is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422100027115
Unscheduled inspection
Start date: 2021-02-26, end date: 2021-03-04, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development
# 422100024988
Unscheduled inspection
Start date: 2021-02-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422105305025
Unscheduled inspection
Start date: 2021-01-19, end date: 2021-01-29, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of design documentation and verification of compliance with the requirements of Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422005282838
Unscheduled inspection
Start date: 2020-12-23, end date: 2020-12-29, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation Tasks verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development
# 422005282825
Unscheduled inspection
Start date: 2020-12-23, end date: 2020-12-29, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation Tasks verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development
# 422005282008
Unscheduled inspection
Start date: 2020-12-23, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422005258051
Unscheduled inspection
Start date: 2020-12-02, end date: 2020-12-08, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation Tasks verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development
# 422005226922
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-11-18, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 422005233930
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-11-27, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta ustroistvo monolitnogo karkasa a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii v sootvetstvii s p3 programmy proverok 1 utverzhdennoi prikazom 15201OS ot 28022020zadachei nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstvapredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422005212152
Unscheduled inspection
Start date: 2020-11-25, end date: 2020-12-01, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities
# 422005185784
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-20, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422005185781
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-20, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422005185779
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-20, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422005230036
Unscheduled inspection
Start date: 2020-10-23, end date: 2020-10-27, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422005187221
Unscheduled inspection
Start date: 2020-10-21, end date: 2020-10-27, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities
# 422005178233
Unscheduled inspection
Start date: 2020-10-14, end date: 2020-10-20, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities
# 422005178184
Unscheduled inspection
Start date: 2020-10-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422004712930
Unscheduled inspection
Start date: 2020-08-19, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422004460380
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-07-29, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004460333
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-07-29, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004487280
Unscheduled inspection
Start date: 2020-07-28, end date: 2020-08-03, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: It is carried out in order to verify the conformity of the work performed and the building materials used during the construction of the facility.
# 422004469833
Unscheduled inspection
Start date: 2020-07-28, end date: 2020-08-03, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: s celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obektaZadachei nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004463503
Unscheduled inspection
Start date: 2020-07-23, end date: 2020-07-29, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities
# 422004456779
Unscheduled inspection
Start date: 2020-07-16, end date: 2020-07-22, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities
# 422004439151
Unscheduled inspection
Start date: 2020-06-25, end date: 2020-06-29, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of verifying the compliance of the work performed and the building materials used in the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and verifying compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004420770
Unscheduled inspection
Start date: 2020-06-03, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422004420761
Unscheduled inspection
Start date: 2020-06-03, end date: 2020-06-09, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities
# 422004435578
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-06-29, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obektazadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004435577
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422004435576
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422004432349
Unscheduled inspection
Start date: 2020-06-15, end date: 2020-06-17, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obektazadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004405173
Unscheduled inspection
Start date: 2020-05-08, end date: 2020-05-15, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation Tasks verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development
# 422004405166
Unscheduled inspection
Start date: 2020-05-08, end date: 2020-05-15, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation Tasks verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility Subject verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development
# 422004405915
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-05-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Proverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta ustroistvo monolitnogo karkasa i vnutrikvartalnyh i vnutridomovyh inzhenernyh setei a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii zadachei nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004405993
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-05-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Verification of the compliance of the work performed and the building materials used during the construction of the facility excavation, pile driving, grillwork, and the results of such work with the requirements of the design documentation for verifying compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation the objective of this audit is to comply with the mandatory requirements of the legislation of the Russian Federation on urban planning activities during construction. mandatory requirements of the legislation of the Russian Federation on urban development activities
# 422004405793
Unscheduled inspection
Start date: 2020-05-14, end date: 2020-05-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: compliance of the work performed and the building materials used during the construction of the facility The objective of this check is to comply with the legislation of the Russian Federation on urban development activities during construction and to comply with the legislation of the Russian Federation on urban development activities
# 422004407383
Unscheduled inspection
Start date: 2020-05-13, end date: 2020-05-19, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Verification of the compliance of the work performed and the building materials used in the course of work with the requirements of the design documentation The objective of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban development activities during the construction of a capital construction facility and to comply with the mandatory requirements of the legislation of the Russian Federation in the field of urban development
# 422004410267
Unscheduled inspection
Start date: 2020-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422004386606
Unscheduled inspection
Start date: 2020-04-01, end date: 2020-04-07, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of the work with the requirements of the design documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban development activities during the construction of a capital construction facility and to comply with the mandatory requirements of the legislation of the Russian Federation in the field of urban development
# 422004386775
Unscheduled inspection
Start date: 2020-04-01, end date: 2020-04-03, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: S celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta ustroistvo kotlovana zabivka svai ustroistvo rostverkov a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii zadachei nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004404856
Unscheduled inspection
Start date: 2020-04-30, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422004404855
Unscheduled inspection
Start date: 2020-04-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422004368868
Unscheduled inspection
Start date: 2020-03-18, end date: 2020-03-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of verifying the compliance of the work performed and the building materials used during the construction of a capital construction facility with the requirements of the design documentation and in order to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004368856
Unscheduled inspection
Start date: 2020-03-18, end date: 2020-03-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of verifying the compliance of the work performed and the building materials used during the construction of a capital construction facility with the requirements of the design documentation and in order to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004358379
Unscheduled inspection
Start date: 2020-03-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422004262869
Unscheduled inspection
Start date: 2020-02-11, end date: 2020-02-13, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii i proverki vypolneniya trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii Zadachei i predmetom nastoyaschei proverki yavlyaetsya soblyudenie trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva
# 422004255489
Unscheduled inspection
Start date: 2020-02-12, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422004237640
Unscheduled inspection
Start date: 2020-02-12, end date: 2020-02-18, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: compliance of the work performed and the building materials used during the construction of the facility, the installation of internal engineering networks, the finishing of the MOF, as well as the results of such work, with the requirements of the design documentation for verifying compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation. The purpose of this audit is to comply with the mandatory requirements of the legislation of the Russian Federation on urban planning activities during construction. The subject of this audit is compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities during construction. requirements of the legislation of the Russian Federation on urban development activities
# 422004221500
Unscheduled inspection
Start date: 2020-01-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421904073068
Unscheduled inspection
Start date: 2019-12-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421904072777
Unscheduled inspection
Start date: 2019-12-17, end date: 2019-12-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421904042468
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-12-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421904042417
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-12-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903975582
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-12-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903934681
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903934628
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903975799
Unscheduled inspection
Start date: 2019-11-14, end date: 2019-11-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903975780
Unscheduled inspection
Start date: 2019-11-14, end date: 2019-11-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903882311
Unscheduled inspection
Start date: 2019-10-22, end date: 2019-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903810478
Unscheduled inspection
Start date: 2019-10-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 421903850258
Unscheduled inspection
Start date: 2019-10-15, end date: 2019-10-17, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903834275
Unscheduled inspection
Start date: 2019-10-15, end date: 2019-10-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903061100
Unscheduled inspection
Start date: 2019-09-10, end date: 2019-09-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903189347
Unscheduled inspection
Start date: 2019-09-10, end date: 2019-09-16, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903594877
Unscheduled inspection
Start date: 2019-09-18, end date: 2019-09-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903475046
Unscheduled inspection
Start date: 2019-09-18, end date: 2019-09-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903475013
Unscheduled inspection
Start date: 2019-09-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421902980639
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-09-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902991138
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902891126
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902976830
Unscheduled inspection
Start date: 2019-08-22, end date: 2019-08-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Cel proverka ispolneniya predpisaniya inspekcii 01741401 ot 23052019 zadacha proverka ustraneniya narushenii pri osuschestvlenii stroitelstva predmet ispolnenie predpisaniya inspekcii 01741401 ot 23052019
# 421902932940
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902891110
Unscheduled inspection
Start date: 2019-08-05, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 421903060144
Unscheduled inspection
Start date: 2019-08-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421903060094
Unscheduled inspection
Start date: 2019-08-29, end date: 2019-09-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902916796
Unscheduled inspection
Start date: 2019-08-07, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 421902914408
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902914377
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902830803
Unscheduled inspection
Start date: 2019-07-12, end date: 2019-07-16, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902854966
Unscheduled inspection
Start date: 2019-07-09, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 421902854928
Unscheduled inspection
Start date: 2019-07-09, end date: 2019-07-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902847300
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902847248
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902847149
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902739549
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902784810
Unscheduled inspection
Start date: 2019-06-20, end date: 2019-06-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902739918
Unscheduled inspection
Start date: 2019-06-20, end date: 2019-06-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902813100
Unscheduled inspection
Start date: 2019-06-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421902678314
Unscheduled inspection
Start date: 2019-05-14, end date: 2019-05-16, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902678900
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-05-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902678340
Unscheduled inspection
Start date: 2019-05-21, end date: 2019-05-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902685405
Unscheduled inspection
Start date: 2019-05-20, end date: 2019-05-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902685281
Unscheduled inspection
Start date: 2019-05-28, end date: 2019-05-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902690674
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902690575
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902690563
Unscheduled inspection
Start date: 2019-04-30, end date: 2019-05-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902628829
Unscheduled inspection
Start date: 2019-04-22, end date: 2019-04-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning