# 471800309723
Unscheduled inspection
Start date: 2018-04-18, end date: 2018-05-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 471800105070
Unscheduled inspection
Start date: 2018-02-21, end date: 2018-03-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 47170701457559
Unscheduled inspection
Start date: 2017-03-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 47170701371359
Unscheduled inspection
Start date: 2017-02-08, end date: 2017-03-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification. The purpose of this verification is to comply with mandatory requirements, including compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency requirements and equipment requirements for the capital construction facility accounting for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation