# 772004244347
Unscheduled inspection
Start date: 2020-02-04, end date: 2020-02-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771904098854
Unscheduled inspection
Start date: 2019-12-13, end date: 2020-01-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notice from the developer to the customer. The tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person. The subject is to verify the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for used energy resourcescompliance with the instructions of the Moscow City Construction Supervision
# 771903854386
Unscheduled inspection
Start date: 2019-10-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803478936
Unscheduled inspection
Start date: 2019-08-20, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77190803426335
Unscheduled inspection
Start date: 2019-05-31, end date: 2019-06-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: This audit is carried out in order to carry out control measures in connection with the verification of the fulfillment of an order based on the expiration of the deadline for the fulfillment by a legal entity, an individual entrepreneur, of an order issued by the state construction supervision authority to eliminate violations of mandatory requirements from 25032019 209719. The objectives of this audit are to prevent identify and suppress violations of the requirements of the design documentation of legislation on urban development by the person being audited. The subject of this audit is The purpose is to check the elimination of violations specified in the order issued by Mosgosstroynadzor 209719 dated 25032019
# 77190803409914
Unscheduled inspection
Start date: 2019-05-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803371478
Unscheduled inspection
Start date: 2019-03-19, end date: 2019-03-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: this audit is conducted in order to carry out control measures in connection with the implementation of the audit program based on the approved audit program bn dated 11042017the objectives of this audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited personthe subject of this audit is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources.
# 77190803316846
Unscheduled inspection
Start date: 2019-01-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803246607
Unscheduled inspection
Start date: 2018-10-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803184372
Unscheduled inspection
Start date: 2018-07-20, end date: 2018-07-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803159554
Unscheduled inspection
Start date: 2018-06-14, end date: 2018-06-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803138608
Unscheduled inspection
Start date: 2018-05-16, end date: 2018-05-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803109376
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-03-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803089297
Unscheduled inspection
Start date: 2018-02-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803068965
Unscheduled inspection
Start date: 2018-01-25, end date: 2018-01-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802893126
Unscheduled inspection
Start date: 2017-11-24, end date: 2017-11-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170801938379
Unscheduled inspection
Start date: 2017-08-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701689554
Unscheduled inspection
Start date: 2017-06-09, end date: 2017-06-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701585553
Unscheduled inspection
Start date: 2017-04-28, end date: —, duration: —
Authority: —
Purpose of inspection: