# 272100222642
Unscheduled inspection
Start date: 2021-05-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272100012581
Unscheduled inspection
Start date: 2021-02-19, end date: 2021-03-22, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out for the purpose of carrying out regional state construction supervision on the basis of the notice on the completion dates of the works to be inspected dated 02/09/2021 b/n (ex. No. 478 dated 02/10/2021).
The objectives of this audit are: prevention, detection, and suppression of violations of current legislation on urban development and project documentation.
The subject of the audit is to verify that the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used.
# 271801990927
Unscheduled inspection
Start date: 2018-10-25, end date: 2018-11-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 13042017. The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation. The subject of the inspection is to verify the compliance of the work performed and the construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work with the requirements of the design documentation. documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for used energy resources.
# 271801997321
Unscheduled inspection
Start date: 2018-10-26, end date: 2018-11-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of StroyCom Everest LLC on the completion of the construction of a capital construction facility dated 16102018 bn vx 5067 dated 16102018. The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation. The subject of the inspection is to verify the compliance of the work and the construction materials used in the process construction reconstruction of the capital construction facility as well as the results of such work to the requirements of the design documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and to the requirements for equipping the capital construction facility with metering devices for energy resources used
# 271800348796
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-06-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of StroyCom Everest LLC on the completion of the construction of a capital construction facility dated 250-42018 bn bx 1849 dated 250-42018 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentation. The subject of this inspection is to verify the compliance of the work and the use of building materials during the construction of the Facility as well as the results of such work to meet the requirements of technical regulations and project documentation
# 271800240805
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 13042017. The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentation. The subject of this inspection is to verify the compliance of work and the use of building materials during the construction of the Facility, as well as the results of such inspections. works according to the requirements of the technical regulations of the project documentation
# 271800240784
Unscheduled inspection
Start date: 2018-03-30, end date: 2018-04-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out for the purpose of implementing regional state construction supervision on the basis of a notice from StroyCom Everest LLC on the execution of an order dated March 22, 2018 on the elimination of violations during the construction of a capital construction facility issued by the state construction supervision authority. The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentation The subject of this check is the verification of the execution of the Prescription
# 27170802955725
Unscheduled inspection
Start date: 2017-12-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 27170802960771
Unscheduled inspection
Start date: 2017-12-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 27170802752846
Unscheduled inspection
Start date: 2017-10-19, end date: 2017-11-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this audit is conducted for the purpose of implementing regional state construction supervision on the basis of the notice of completion of the capital construction facility dated October 04, 2017 BN VX 4696 dated October 04, 2017The objectives of this audit are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentationthe subject of this audit is to verify compliance with works and the use of building materials during the construction of the Facility as well as the results of such work to the requirements of the technical regulations of the project documentation
# 27170802752827
Unscheduled inspection
Start date: 2017-10-19, end date: 2017-11-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of notices from the developer StroyCom Everest LLC on the elimination of violations during the construction of a capital construction facility dated October 04, 2017 bn VH 4697 dated 04102017 on the execution of the instruction from 30062017 C07417 issued by the state construction supervision authority The objectives of this inspection are to prevent detect and suppress violations of current legislation on urban development including technical regulations and project documentationthe subject of this audit is to verify the fulfillment of the Prescription
# 27170701727726
Unscheduled inspection
Start date: 2017-06-30, end date: 2017-07-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program for the Facility dated February 15, 2016The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentationthe subject of the inspection is to verify the conformity of the work performed and the building materials used during the construction of the Facility and the results of such work are required by the technical regulations of the project documentation
# 27170701670621
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-06-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision in connection with the expiration of the deadline for StroyCom Everest LLC to comply with the regulations dated 20012017 C0142017 on the elimination of violations during the construction of a capital construction facility issued by the state construction supervision authority. The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentationthe subject of this inspection it is a verification of the fulfillment of the Prescription
# 27160701240596
Unscheduled inspection
Start date: 2016-12-26, end date: 2017-01-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of the developer StroyCom Everest LLC dated December 08, 2016 bn on the completion of the construction of the BX 5142 Facility dated December 09, 2016The purpose of this inspection is to monitor compliance by construction participants with the legislation on urban development activities. The purpose of this inspection is to verify the compliance of the work and the construction materials used during construction The object as well as the results of such work meet the requirements of the technical regulations of the project documentation
# 27160701095579
Unscheduled inspection
Start date: 2016-11-16, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection:
# 27160601742147
Unscheduled inspection
Start date: 2016-07-27, end date: 2016-08-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision in connection with the notice dated 18072016 from StroyKom Everest bn LLC on the elimination of violations during the construction of a capital construction facility according to the order dated June 16, 2016 C01052016 on the elimination of violations during the construction of a capital construction facility hereinafter referred to as the Order issued by the state construction supervision authority The task of this inspection is to monitor compliance by construction participants The subject of this audit is the verification of the implementation of the Regulation on urban development activities.