# 361800751106
Unscheduled inspection
Start date: 2018-09-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 361800631700
Unscheduled inspection
Start date: 2018-08-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 361800393160
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-21, duration: —
Authority: CentralnoCHernozemnoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: Establishing compliance with licensing requirements for the condition of premises buildings structures equipment and specialized installations specially equipped and equipped with special signs of vehicles that are supposed to be used by the license applicant in carrying out the licensed type of activity and the availability of employees necessary for carrying out the licensed type of activity
# 361800364214
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-18, duration: —
Authority: CentralnoCHernozemnoe mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya
Purpose of inspection: assessment of compliance of the information contained in the submitted application for a license and the documents attached to it with the provisions of Parts 1 and 3 of Article 13 of the Federal Law On Licensing of Certain Types of Activities
# 361800033848
Unscheduled inspection
Start date: 2018-01-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 36160700117396
Unscheduled inspection
Start date: 2016-09-12, end date: 2016-09-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer. The verification is compliance with mandatory requirements or requirements established by municipal legal acts
# 36160601685760
Unscheduled inspection
Start date: 2016-06-24, end date: 2016-06-29, duration: —
Authority: Upravlenie gosavtodornadzora po Voronezhskoi oblasti
Purpose of inspection: vypolnenie ranee vydannogo predpisaniya ot 30052016 7 srok ispolneniya kotorogo istek 16062016 g
# 36150601439844
Unscheduled inspection
Start date: 2015-12-28, end date: —, duration: —
Authority: Upravlenie gosavtodornadzora po Voronezhskoi oblasti
Purpose of inspection: