# 772004371362
Unscheduled inspection
Start date: 2020-03-23, end date: 2020-03-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772004296697
Unscheduled inspection
Start date: 2020-02-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903980139
Unscheduled inspection
Start date: 2019-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903548737
Unscheduled inspection
Start date: 2019-09-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803474453
Unscheduled inspection
Start date: 2019-08-06, end date: 2019-08-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803420881
Unscheduled inspection
Start date: 2019-05-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803113726
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803096221
Unscheduled inspection
Start date: 2018-03-02, end date: 2018-03-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170803029703
Unscheduled inspection
Start date: 2017-12-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802898093
Unscheduled inspection
Start date: 2017-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701483477
Unscheduled inspection
Start date: 2017-03-23, end date: 2017-04-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77160701280860
Unscheduled inspection
Start date: 2016-12-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160700062470
Unscheduled inspection
Start date: 2016-08-23, end date: 2016-08-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 809116 ot 04082016
# 77160601749457
Unscheduled inspection
Start date: 2016-07-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: