# 742004235185
Unscheduled inspection
Start date: 2020-02-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742004231047
Unscheduled inspection
Start date: 2020-01-28, end date: 2020-02-03, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the installation of external and internal gas supply networks and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code. If the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 Availability of a construction permit 3 Meeting the requirements of HR 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741904043748
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-17, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of work on the Warehouse of finished products with the installation of a membrane roof in the process of work, the installation of a monolithic floor slab in the process of work, the installation of internal engineering networks in the process of work, the installation of external on-site networks and structures in the process of work, the Administrative building, the installation of external on-site networks and structures in the process of work, the pumping station, and construction work in the process of work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model if the formation and maintenance of information models are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used2 The availability of a construction permit3 Compliance with the requirements of HH 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741903987433
Unscheduled inspection
Start date: 2019-11-21, end date: 2019-11-27, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of excavation works on trench construction installation of an underground gas pipeline electrochemical protection of a gas pipeline reclamation and construction materials used during construction reconstruction of a capital construction facility as well as the results of such work with the requirements of the design documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, taking into account changes made to the design documentation in accordance with parts 38 and 39 of Article 49 of this Code and or an information model if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources2 Availability of a construction permit 3 Implementation requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741903841830
Unscheduled inspection
Start date: 2019-10-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741903797418
Unscheduled inspection
Start date: 2019-10-21, end date: 2019-10-25, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 the work at the Warehouse of finished products, the installation of the metal frame of the building after completion of installation of walling the walls of the sandwich after completion of installation of profiled sheeting of the roof after completion of the membrane roof in the process of work arrangement of monolithic floor slab after completion of the installation of technological equipment in the process of performance the installation of internal engineering networks in the process of performance the installation of external networks and structures in the process of work Administrativetools case the installation of external networks and structures in the process of performance Pump stroitelnomontazhnyh work in progress of works and construction materials used in the construction process of reconstruction of capital construction object as well as the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy ресурсов2 have permission to строительство3 fulfillment of the requirements of CC 23 and 31 ст52 Urban code
# 741903731573
Unscheduled inspection
Start date: 2019-10-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902988479
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-06, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the Warehouse of finished products with the installation of the foundation after completion of the work, the installation of metal structures of the building frame during the work, the installation of enclosing structures of walls made of sandwich panels during the work, the installation of profiled roofing during the work, the installation of a membrane roof during the work, the installation of a monolithic floor slab during the work, the installation of external indoor networks and structures during the execution of work, the Administrative building, the installation of external on-site networks and structures during the execution of work, the pumping station, construction work during the execution of work, the boiler house, construction work during the execution of work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, project documentation2 The availability of a construction permit,3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code Russian Federation
# 741902973054
Unscheduled inspection
Start date: 2019-08-29, end date: 2019-09-04, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the preparation of the construction site with excavation work on the construction of a trench installation of an underground gas pipeline and the construction materials used during the construction of a capital construction facility as well as the results of such work with project documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 2 3 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741902972857
Unscheduled inspection
Start date: 2019-08-29, end date: 2019-09-04, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of excavation work on trench construction, installation of an underground gas pipeline and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with project documentation2 Availability of a construction permit 3 Compliance with the requirements of hr 2 3 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741902900700
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-06, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the preparation of the construction site with excavation work on the construction of a trench installation of an underground gas pipeline and the construction materials used during the construction of a capital construction facility as well as the results of such work with project documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 2 3 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741902754613
Unscheduled inspection
Start date: 2019-06-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902811313
Unscheduled inspection
Start date: 2019-06-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902715652
Unscheduled inspection
Start date: 2019-05-22, end date: 2019-05-28, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the construction of a water pipeline in the area from the Magistral store to the tableware market with the construction of a water pipeline in the area from Sportivnaya Street to Pobedy Street and Mira Quarter "E" street and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741902658884
Unscheduled inspection
Start date: 2019-04-23, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 741801525998
Unscheduled inspection
Start date: 2018-09-19, end date: 2018-10-16, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the completed facility 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800681384
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-14, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the excavation work for the installation of the gas pipeline from PC 280 to PC 320 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800556811
Unscheduled inspection
Start date: 2018-07-31, end date: 2018-08-06, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the excavation work for the installation of the gas pipeline from PC 260 to PC 280 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800488065
Unscheduled inspection
Start date: 2018-06-27, end date: 2018-07-03, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the excavation work for the installation of the gas pipeline from PC 240 to PC 260 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800327915
Unscheduled inspection
Start date: 2018-05-15, end date: 2018-05-21, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the excavation work for the installation of the gas pipeline from PK 220 to PK 240 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800362290
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-05-25, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the actual condition of the object 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800252209
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-04-13, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the complex of earthworks for foundations, backfilling, installation of metal structures of the building frame and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a building permit 3 Compliance with the requirements of hh 23 and 31 st52 Urban Planning Code of the Russian Federation
# 741800252291
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-04-13, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the installation of metal frame structures in the 58J axes and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 Urban Planning Code of the Russian Federation
# 741800249742
Unscheduled inspection
Start date: 2018-04-03, end date: 2018-04-09, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the excavation work for the installation of the gas pipeline from PK 200 to PK 220 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800212573
Unscheduled inspection
Start date: 2018-03-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800212556
Unscheduled inspection
Start date: 2018-03-26, end date: 2018-03-30, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1conformity of the work on concreting foundation slabs and retaining walls, backfilling, installation of metal structures of the building frame and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800092777
Unscheduled inspection
Start date: 2018-02-22, end date: 2018-03-01, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the excavation work for the installation of the gas pipeline from PK 194 to PK 227 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 74180803053379
Unscheduled inspection
Start date: 2018-01-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74180803053520
Unscheduled inspection
Start date: 2018-01-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74170802873488
Unscheduled inspection
Start date: 2017-11-27, end date: 2017-12-01, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 The actual condition of the capital construction facility 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 74170802852394
Unscheduled inspection
Start date: 2017-11-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74170701543939
Unscheduled inspection
Start date: 2017-04-20, end date: 2017-04-26, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 The compliance of the trench development work, the installation of an underground gas pipeline, the installation of an above-ground gas pipeline and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 The availability of a construction permit 3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74170701316762
Unscheduled inspection
Start date: 2017-02-01, end date: 2017-02-07, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the construction of the gas pipeline from PK01+285 to PK02+628 and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3compliance with the requirements of HR 23 st52 of the Urban Planning Code of the Russian Federation
# 74170701298052
Unscheduled inspection
Start date: 2017-01-18, end date: 2017-01-24, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The actual condition of the capital construction facility 2The receipt of a construction permit 3The observance of the requirements of HR 23 Art 52 of the Urban Planning Code of the Russian Federation
# 74170701285717
Unscheduled inspection
Start date: 2017-01-17, end date: 2017-01-23, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work performed during the construction of the trench, filling the bottom of the trench with sand, laying pipes during the installation of wells with the installation of fittings during the backfilling of the laid network along 5 Street and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74170701304482
Unscheduled inspection
Start date: 2017-01-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74160701228169
Unscheduled inspection
Start date: 2016-12-14, end date: 2016-12-20, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work performed during the construction of the trench, filling the bottom of the trench with sand, laying pipes during the installation of wells with the installation of fittings during the backfilling of the laid network along 3 Street and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74160701159985
Unscheduled inspection
Start date: 2016-11-29, end date: 2016-12-02, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the installation of the internal steel gas pipeline installation of the base for boilers and tanks installation of cranes installation of equipment for priming and painting the internal steel gas pipeline and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2The presence of a building permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74160601792836
Unscheduled inspection
Start date: 2016-08-15, end date: —, duration: —
Authority: —
Purpose of inspection: