# 432101444354
Unscheduled inspection
Start date: 2021-12-24, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Kirovskoi oblasti
Purpose of inspection:
# 432101261667
Unscheduled inspection
Start date: 2021-10-28, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Kirovskoi oblasti
Purpose of inspection:
# 432101123422
Unscheduled inspection
Start date: 2021-10-05, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Kirovskoi oblasti
Purpose of inspection:
# 432100498456
Unscheduled inspection
Start date: 2021-08-24, end date: —, duration: 6
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Kirovskoi oblasti
Purpose of inspection: Objectives: Implementation of the verification program
Tasks: Prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and design and working documentation committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer
Subject: 1) compliance of the work performed and the construction materials and products used in the process of construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 article 49 of the Urban Planning Code of the Russian Federation) and (or) the information model;
2) the requirements for a construction permit, as well as the parameters of the capital construction facility under construction, under reconstruction, specified in the construction permit;
3) the requirements established by Parts 2 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation;
4) the requirements established by part 4 of Article 52 of the Urban Planning Code of the Russian Federation to ensure the conservation of the capital construction facility;
5) requirements for the procedure for the implementation of construction control established by the Urban Planning Code of the Russian Federation and other regulatory legal acts.
# 432100309521
Unscheduled inspection
Start date: 2021-06-30, end date: —, duration: 6
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Kirovskoi oblasti
Purpose of inspection: Objectives: Implementation of the verification program
Tasks: Prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and project documentation committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer
Subject: Compliance with mandatory requirements or requirements established by municipal legal acts
# 111800587654
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-10, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: provedenie proverki po kontrolyu vypolneniya ranee vydannogo predpisaniya 108 ot 08062018 g preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii soblyudenie obyazatelnyh trebovanii
# 111800394842
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-08, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: conducting an inspection in accordance with the inspection program prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the technical customer, compliance with mandatory requirements
# 11170802931112
Unscheduled inspection
Start date: 2017-12-04, end date: —, duration: —
Authority: —
Purpose of inspection: