# 162005223900
Unscheduled inspection
Start date: 2020-11-11, end date: 2020-11-11, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate from 05112020 12271 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 12102020 1212099701 to 12112020G Tasks The purpose of this audit is to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationthe purpose of this audit is to comply with the instructions of state control bodies, supervision bodies, and municipal control bodies.
# 162005224298
Unscheduled inspection
Start date: 2020-11-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005223879
Unscheduled inspection
Start date: 2020-11-11, end date: 2020-11-11, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the Inspection notice dated 05112020 12271 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 12102020 1212099101 to 12112020G Tasks The purpose of this audit is to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationthe purpose of this audit is to comply with the instructions of state control bodies, supervision bodies, and municipal control bodies.
# 162005224255
Unscheduled inspection
Start date: 2020-11-11, end date: 2020-11-11, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as to draw up an inspection report on the completed construction of the facility in accordance with the received by notification dated 09112020 12315 to the Inspection on the completion of the construction of the capital construction facility, the objectives of this inspection are to prevent, identify and prevent violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts
# 161903937260
Unscheduled inspection
Start date: 2019-11-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903931363
Unscheduled inspection
Start date: 2019-11-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903809481
Unscheduled inspection
Start date: 2019-10-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903809425
Unscheduled inspection
Start date: 2019-10-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902696313
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-05-16, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 10042019 case 121820130023 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161902728053
Unscheduled inspection
Start date: 2019-05-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170802995147
Unscheduled inspection
Start date: 2017-12-19, end date: 2017-12-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out within the framework of the regional state construction supervision registration number of the function in the federal state information system "Federal Register of State and Municipal Services of Functions" 1600000000160066730 Establish that this inspection is carried out in order to determine the compliance of eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the received to the Inspection of the notification dated 13122017 10427 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which were ordered to be eliminated within the time limit set by the instruction from 01122017 1219139801 to 22012018the tasks of this inspection are the prevention, as well as the detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the works performed during the construction of the capital construction facility The purpose of this audit is to select the required compliance with the mandatory requirements and or requirements established by municipal legal acts.
# 16170802894177
Unscheduled inspection
Start date: 2017-11-28, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170802778129
Unscheduled inspection
Start date: 2017-10-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170701624861
Unscheduled inspection
Start date: 2017-05-22, end date: 2017-05-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the completed works used in the process of construction reconstruction of an object of capital construction of building materials, the results of such works with the requirements of technical regulations of project documentation, the objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of an object of capital construction with the requirements of technical requirements regulations, other regulatory legal acts and project documentation The subject of this audit is compliance with mandatory requirements