# 662101369594
Unscheduled inspection
Start date: 2021-11-26, end date: 2021-12-17, duration: 16
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out on the basis of a notice of completion of the construction of a capital construction facility. No. 29-01-41/50630 dated 11/17/2021, in accordance with the inspection program dated 09/20/2021 No. 29-18-01/320-19, the task of this inspection is to carry out regional state construction supervision. The subject of this audit is: verification of the conformity of the work performed and the building materials used during the construction of the capital construction facility "Stage 1 of construction, includes: construction of a warehouse in axes A-B/1-21 with internal engineering and technical support networks; construction of external fire extinguishing networks (B2) with structures (according to the general plan no. 2); construction of storm sewer networks along the main and courtyard facades of the warehouse with stormwater tanks (according to general plan No. 3a, b, c); transfer of TP and construction of 0.4 kV and 10 kV power supply networks; construction of heating networks; construction of household and industrial sewerage from the warehouse with tanks for receiving industrial and household wastewater; installation of outdoor lighting fixtures on the walls of the warehouse along the perimeter; installation of communication networks for the warehouse; paving of driveways, platforms on the territory adjacent to the warehouse from the facility: Finished goods warehouse with ABC, correction at the address: Sverdlovsk region, Kamyshlovsky district, Obukhovskoye village, Shkolnaya Street, 45-b", located at the address: Sverdlovsk region, Kamyshlovsky district, Obukhovskoye village, Shkolnaya str., 45-b, as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of the Article 49 of the Urban Planning Code of the Russian Federation) and (or) the information model (if the formation and maintenance of the information model are mandatory
# 662100417963
Unscheduled inspection
Start date: 2021-08-09, end date: 2021-08-20, duration: 10
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to control the execution of a previously issued instruction on the elimination of identified violations; Tasks - the implementation of regional state construction supervision; Subject - the implementation of a previously issued instruction on the elimination of an identified violation of mandatory requirements
# 662100360781
Unscheduled inspection
Start date: 2021-07-22, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 662100191707
Unscheduled inspection
Start date: 2021-05-13, end date: 2021-06-09, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program No. 29-18-01/320-19 dated 2020-12-10; The tasks are to carry out regional state construction supervision; The subject is to verify the conformity of work performed and applicable building materials during the construction of a capital construction facility: Warehouse of finished products with ABC, correction at the address: Sverdlovsk region, Kamyshlovsky district, Obukhovskoye village, Shkolnaya Street, 45-b, located at: Sverdlovsk region, Kamyshlovsky district, Obukhovskoye village, Shkolnaya Street, 45-b, the results of such work to the requirements approved in accordance with parts 15, 15.2 and 15.3 Article 48 of the Urban Planning Code of the Russian Federation of the project documentation, including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code. the Code of the Russian Federation.
# 662100016900
Unscheduled inspection
Start date: 2021-02-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 662105280421
Unscheduled inspection
Start date: 2021-01-11, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 662004450831
Unscheduled inspection
Start date: 2020-07-09, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 661904116301
Unscheduled inspection
Start date: 2019-12-17, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 661903872790
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-11-20, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the developer's notice on the start of construction of the capital construction facility bx dated 13092019 41538 The task is to carry out regional state construction supervision The subject is to verify the compliance of the work and the construction materials used during the construction of the capital construction facility "Warehouse of finished products at the address Sverdlovsk region Kamyshlovsky district with Obukhovskoye ul. School 45b" located at the address Sverdlovsk region Kamyshlovsky district village Obukhovskoye 45b Shkolnaya Street as well as the results of such work meet the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements established by parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation