Found 54 inspections:

# 002004354171
Unscheduled inspection
Start date: 2020-03-16, end date: 2020-04-10, duration:
Authority: Gosudarstvennaya inspekciya truda v Kemerovskoi oblasti
Purpose of inspection: Celi Osuschestvlenie federalnogo gosudarstvennogo nadzora za soblyudeniem yuridicheskim licom ili individualnym predprinimatelem obyazatelnyh trebovanii trudovogo zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava Poruchenie Rostruda 422620PO ot 14022020 ZadachiObespechenie soblyudeniya i zaschity trudovyh prav i svobod grazhdan vklyuchaya pravo na bezopasnye usloviya truda Predmetsoblyudenie obyazatelnyh trebovanii i ili trebovanii ustanovlennyh municipalnymi pravovymi aktami


# 422101364684
Unscheduled inspection
Start date: 2021-11-23, end date: —, duration: 20
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the completed works and the applied building materials and products during construction, as well as the results of such work with the requirements of the project documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Civil Code of the Russian Federation, are part of such project documentation) The task is to determine the compliance of the constructed capital construction facility with the requirements of the design documentation. The subject is compliance with the mandatory requirements of the legislation of the Russian Federation on urban development


# 422101245840
Unscheduled inspection
Start date: 2021-10-29, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials and products used in the course of work with the requirements of the project documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Civil Code of the Russian Federation, are part of such project documentation). The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 422100540692
Unscheduled inspection
Start date: 2021-08-31, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials and products used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 422100377496
Unscheduled inspection
Start date: 2021-07-27, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials and products used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 422100365509
Unscheduled inspection
Start date: 2021-07-27, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials and products used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 422100291027
Unscheduled inspection
Start date: 2021-06-11, end date: —, duration: 20
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of checking the compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work, with the requirements of design documentation and checking compliance with the requirements of Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the task and subject of this check is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction


# 422100227278
Unscheduled inspection
Start date: 2021-05-18, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: proverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii, inyh normativnyh aktov, proverki vypolneniya trebovanii chastei 2, 3, 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii; zadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva; predmetom nastoyaschei proverki yavlyaetsya: soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti


# 422100227077
Unscheduled inspection
Start date: 2021-05-31, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 422100109550
Unscheduled inspection
Start date: 2021-04-06, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 422100152235
Unscheduled inspection
Start date: 2021-04-22, end date: 2021-04-28, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Cel: proverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe vypolneniya rabot trebovaniyam proektnoi dokumentacii, proverki vypolneniya trebovanii chastei 2, 3, 3.1 stati 52 Gradostroitelnogo kodeksa RF. Zadacha nastoyaschei proverki yavlyaetsya soblyudenie trebovanii zakonodatelstva Rossiiskoi Federacii v oblasti gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva obekta kapitalnogo stroitelstva. Predmet: soblyudenie obyazatelnyh trebovanii zakonodatelstva Rossiiskoi Federacii v oblasti gradostroitelnoi deyatelnosti.


# 422100059368
Unscheduled inspection
Start date: 2021-03-15, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: proverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii, inyh normativnyh aktov, proverki vypolneniya trebovanii chastei 2, 3, 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii; zadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva; predmetom nastoyaschei proverki yavlyaetsya: soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti


# 422105303622
Unscheduled inspection
Start date: 2021-01-26, end date: 2021-02-01, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 422005296002
Unscheduled inspection
Start date: 2020-12-17, end date: 2020-12-22, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: verification of the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of project documentation and other regulatory acts to verify compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation. The purpose of this audit is to comply with the legislation of the Russian Federation on urban planning activities during construction. The subject of this audit is compliance with the legislation of the Russian Federation about urban planning activities


# 422005199651
Unscheduled inspection
Start date: 2020-10-19, end date: —, duration:
Authority:
Purpose of inspection:


# 422004712402
Unscheduled inspection
Start date: 2020-08-11, end date: 2020-09-04, duration: 19
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: proverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii Zadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva predmetom nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva


# 422004450198
Unscheduled inspection
Start date: 2020-07-13, end date: 2020-07-17, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities


# 422004439666
Unscheduled inspection
Start date: 2020-06-17, end date: 2020-06-19, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: verification of the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of project documentation and other regulatory acts to verify compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation. The purpose of this audit is to comply with the legislation of the Russian Federation on urban planning activities during construction. The subject of this audit is compliance with the legislation of the Russian Federation about urban planning activities


# 422004439665
Unscheduled inspection
Start date: 2020-06-17, end date: —, duration:
Authority:
Purpose of inspection:


# 422004429902
Unscheduled inspection
Start date: 2020-06-16, end date: 2020-06-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose of checking the compliance of the work performed and the construction materials used in the course of work with the requirements of project documentation The purpose of this check is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility Subject to Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning activities


# 422004404997
Unscheduled inspection
Start date: 2020-05-13, end date: 2020-05-15, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: proverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva ustroistvo rostverka montazh vnutrennih i naruzhnyh sten ustroistvo krovli ustroistvo polov elektromontazhnye raboty santehnicheskie raboty otdelochnye raboty fasadnye raboty naruzhnye seti ViK ustroistvo teplotrassy naruzhnye seti elektrosnabzheniya a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii Zadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva predmetom nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva


# 002004354171
Unscheduled inspection
Start date: 2020-03-16, end date: 2020-04-10, duration:
Authority: Gosudarstvennaya inspekciya truda v Kemerovskoi oblasti
Purpose of inspection: Celi Osuschestvlenie federalnogo gosudarstvennogo nadzora za soblyudeniem yuridicheskim licom ili individualnym predprinimatelem obyazatelnyh trebovanii trudovogo zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava Poruchenie Rostruda 422620PO ot 14022020 ZadachiObespechenie soblyudeniya i zaschity trudovyh prav i svobod grazhdan vklyuchaya pravo na bezopasnye usloviya truda Predmetsoblyudenie obyazatelnyh trebovanii i ili trebovanii ustanovlennyh municipalnymi pravovymi aktami


# 422004351296
Unscheduled inspection
Start date: 2020-03-17, end date: 2020-04-13, duration:
Authority: Gosudarstvennaya inspekciya truda v Kemerovskoi oblasti
Purpose of inspection: Osuschestvlenie federalnogogosudarstvennogonadzorazasoblyudeniemyuridicheskimlicomiliindividualnym predprinimatelemobyazatelnyhtrebovaniitrudovogozakonodatelstvaiinyhnormativnyh pravovyhaktovsoderzhaschihnormytrudovogopravaPrikazRostruda4221520PRot 02032020


# 422004369083
Unscheduled inspection
Start date: 2020-03-20, end date: —, duration:
Authority:
Purpose of inspection:


# 422004312291
Unscheduled inspection
Start date: 2020-02-26, end date: 2020-02-28, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: verification of the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of project documentation and other regulatory acts to verify compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation. The purpose of this audit is to comply with the legislation of the Russian Federation on urban planning activities during construction. The subject of this audit is compliance with the legislation of the Russian Federation about urban planning activities


# 421903400874
Unscheduled inspection
Start date: 2019-09-03, end date: 2019-09-03, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Cel proverka ispolneniya predpisaniya inspekcii 390619 ot 14062019 zadacha presechenie i preduprezhdenie narushenii zakonodatelstva ob uchastii v dolevom stroitelstve mnogokvartirnyh domov predmet ispolnenie predpisaniya inspekcii 390619 ot 14062019


# 421902925348
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-05, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development during the construction of a capital construction facility task suppression and prevention of violations of legislation on participation in the shared construction of apartment buildings and or other real estate objects subject to compliance with mandatory requirements of the legislation of the Russian Federation in the field of urban development


# 421903058283
Unscheduled inspection
Start date: 2019-08-29, end date: 2019-09-25, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose verification of compliance of completed works and applied building materials during the construction of the facility as well as the results of such work with the requirements of technical regulations other regulations and design documentation Tasks determination of compliance of the constructed capital construction facility with the requirements of design documentation and technical regulations Subject to compliance with mandatory requirements of the legislation of the Russian Federation on urban development


# 421903059813
Unscheduled inspection
Start date: 2019-08-29, end date: 2019-09-25, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose verification of compliance of completed works and applied building materials during the construction of the facility as well as the results of such work with the requirements of technical regulations other regulations and design documentation Tasks determination of compliance of the constructed capital construction facility with the requirements of design documentation and technical regulations Subject to compliance with mandatory requirements of the legislation of the Russian Federation on urban development


# 421902871291
Unscheduled inspection
Start date: 2019-07-16, end date: 2019-07-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902871131
Unscheduled inspection
Start date: 2019-07-23, end date: 2019-07-29, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902783745
Unscheduled inspection
Start date: 2019-06-13, end date: 2019-06-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421902715288
Unscheduled inspection
Start date: 2019-05-22, end date: —, duration:
Authority:
Purpose of inspection:


# 421902524427
Unscheduled inspection
Start date: 2019-03-05, end date: 2019-03-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421802082532
Unscheduled inspection
Start date: 2018-11-20, end date: 2018-11-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421802157000
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-11-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose verification of compliance of completed works and applied building materials during the construction of the facility as well as the results of such work with the requirements of technical regulations other regulations and design documentation Tasks determination of compliance of the constructed capital construction facility with the requirements of design documentation and technical regulations Subject to compliance with mandatory requirements of the legislation of the Russian Federation on urban development


# 421801902420
Unscheduled inspection
Start date: 2018-10-29, end date: 2018-11-02, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800626237
Unscheduled inspection
Start date: 2018-08-21, end date: —, duration:
Authority:
Purpose of inspection:


# 421800466871
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800420821
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-06-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 001800343795
Unscheduled inspection
Start date: 2018-05-04, end date: 2018-06-01, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu ispolneniya prikaza Rostehnadzora ot 15032017 85 «O proverkah organizacii ekspluatiruyuschih bashennye krany» na osnovanii porucheniya zamestitelya predsedatelya Pravitelstva Rossiiskoi Federacii AG Hloponina ot 08022017 AHP9682 «Ob organizacii i provedenii v period s 2017 po 2019 god vneplanovyh proverok organizacii ekspluatiruyuschih bashennye krany» Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie narushenii obyazatelnyh trebovanii ustanovlennyh federalnymi zakonami i inymi normativnymi aktami Rossiiskoi Federacii v oblasti promyshlennoi bezopasnosti i tehnicheskogo regulirovaniya obyazatelnyh trebovanii prinyatie mer po ustraneniyu narushenii obyazatelnyh trebovanii v sluchae ih vyyavleniya i po privlecheniyu k otvetstvennosti lic dopustivshih narusheniya trebovanii federalnyh zakonov i inyh normativnyh pravovyh aktov Predmetom nastoyaschei proverki yavlyaetsya soblyudenie yuridicheskim licom v processe osuschestvleniya deyatelnosti obyazatelnyh trebovanii promyshlennoi bezopasnosti pri proektirovanii stroitelstve ekspluatacii konservacii i likvidacii opasnyh proizvodstvennyh obektov izgotovlenii montazhe naladke obsluzhivanii i remonte tehnicheskih ustroistv gruzopodemnyh kranov primenyaemyh na opasnyh proizvodstvennyh obektah sootvetstvie ukazannym trebovaniyam ispolzuemyh zdanii pomeschenii sooruzhenii oborudovaniya i materialov a takzhe trebovanii v otnoshenii mashin i oborudovaniya i svyazannyh s trebovaniyami k etoi produkcii processov ekspluatacii i utilizacii


# 421800316217
Unscheduled inspection
Start date: 2018-04-23, end date: 2018-04-27, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose verification of compliance of completed works and applied building materials during the construction of the facility as well as the results of such work with the requirements of technical regulations other regulations and design documentation Tasks determination of compliance of the constructed capital construction facility with the requirements of design documentation and technical regulations Subject to compliance with mandatory requirements of the legislation of the Russian Federation on urban development


# 421800186769
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-04-03, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800186765
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-04-03, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning


# 421800084942
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-01-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802965721
Unscheduled inspection
Start date: 2017-12-13, end date: 2017-12-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802801652
Unscheduled inspection
Start date: 2017-11-08, end date: 2017-11-14, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802906642
Unscheduled inspection
Start date: 2017-11-28, end date: 2017-11-29, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Cel Proverka sootvetstviya vypolnennyh rabot i primenennyh stroitelnyh materialov v processe proizvodstva rabot Zadachi soblyudenie trebovanii zakonodatelstva RF o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva obekta Predmet soblyudenie obyazatelnyh trebovanii zakonodatelstva RF o gradostroitelnoi deyatelnosti


# 42170802906628
Unscheduled inspection
Start date: 2017-11-28, end date: 2017-11-29, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802629309
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-10-17, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities


# 42170802509294
Unscheduled inspection
Start date: 2017-09-21, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:


# 42170802509788
Unscheduled inspection
Start date: 2017-09-21, end date: 2017-09-27, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Cel Proverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe proizvodstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh aktov i proektnoi dokumentacii Zadachi Soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva obekta kapitalnogo stroitelstva Predmet Soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti


# 42170802509384
Unscheduled inspection
Start date: 2017-09-21, end date: —, duration:
Authority:
Purpose of inspection:


# 42160601722428
Unscheduled inspection
Start date: 2016-07-20, end date: 2016-07-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction of a capital construction facility as well as the results of such work with the requirements of technical regulations other regulations and project documentation verification of compliance with the requirements of ch2 ch3 st 52 of the GrK of the Russian Federation Compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.