# 00150601293763
Unscheduled inspection
Start date: 2015-11-02, end date: 2015-11-23, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: ocenka soblyudeniya OOO «Dolomit» obyazatelnyh trebovanii zakonodatelnyh normativnyh pravovyh i normativnyh tehnicheskih dokumentov osuschestvlenie meropriyatii po kontrolyu sostoyaniya ekspluatacii opasnogo proizvodstvennogo obekta Karer po razrabotke mestorozhdeniya dolomitov «Vostochnoe» na osnovanii zhaloby grazhdanina YUriya Kuznecova vhodyaschii O838 ot 13102015 g
# 00150600945950
Unscheduled inspection
Start date: 2015-09-28, end date: 2015-09-30, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya vneplanovaya vyezdnaya proverka provoditsya s celyuispolneniya gosudarstvennoi funkcii po licenzirovaniyu deyatelnosti provedeniya licenzionnogo kontrolya proverki polnoty i dostovernosti licenzionnyh materialov i svedenii o licenziate OOO «Dolomit»
# 74170701485950
Unscheduled inspection
Start date: 2017-04-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74170701418397
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-03-13, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1Sootvetstvie vypolneniya rabot po ustroistvu dvuh tupikovyh derevyannyh uporov v konce zheleznodorozhnyh putei 8 9 i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2Nalichie razresheniya na stroitelstvo3Vypolnenie trebovanii chch 23 st52 Gradostroitelnogo kodeksa RF
# 74170701386405
Unscheduled inspection
Start date: 2017-02-21, end date: 2017-03-01, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the construction of railway tracks 8 useful length 420.59 pm 9 useful length 39686 pm and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74170701285597
Unscheduled inspection
Start date: 2017-01-17, end date: 2017-01-23, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1Fakticheskoe sostoyanie obekta 2Nalichie razresheniya na stroitelstvo3Vypolnenie trebovanii chch 23 st52 Gradostroitelnogo kodeksa RF
# 00150601293763
Unscheduled inspection
Start date: 2015-11-02, end date: 2015-11-23, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: ocenka soblyudeniya OOO «Dolomit» obyazatelnyh trebovanii zakonodatelnyh normativnyh pravovyh i normativnyh tehnicheskih dokumentov osuschestvlenie meropriyatii po kontrolyu sostoyaniya ekspluatacii opasnogo proizvodstvennogo obekta Karer po razrabotke mestorozhdeniya dolomitov «Vostochnoe» na osnovanii zhaloby grazhdanina YUriya Kuznecova vhodyaschii O838 ot 13102015 g
# 00150600945950
Unscheduled inspection
Start date: 2015-09-28, end date: 2015-09-30, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya vneplanovaya vyezdnaya proverka provoditsya s celyuispolneniya gosudarstvennoi funkcii po licenzirovaniyu deyatelnosti provedeniya licenzionnogo kontrolya proverki polnoty i dostovernosti licenzionnyh materialov i svedenii o licenziate OOO «Dolomit»