# 341903936825
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: a this inspection is carried out in accordance with the inspection program in order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and design documentation. The purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation. The subject of this audit is compliance with mandatory requirements regarding the compliance of work performed and construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements approved in accordance with Parts 15 152 and 153 Article 48 of the Urban Planning Code of the Russian Federation hereinafter referred to as the Code of Design Documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources b availability of a construction permit and compliance with the requirements established by Parts 2 3 and 31 of art. 52 of the Urban Planning Code of the Russian Federation
# 341902975454
Unscheduled inspection
Start date: 2019-08-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 341902494242
Unscheduled inspection
Start date: 2019-02-11, end date: 2019-02-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation. The task is to prevent identify and suppress violations of the legislation of the Russian Federation and project documentation. The subject is compliance with mandatory requirements regarding compliance with construction works, their results and the construction materials used to meet the requirements of the project documentation b the availability of a construction permit c the fulfillment of the requirements established by hh 23 and 31 Art 52 of the Urban Planning Code of the Russian Federation
# 341802299318
Unscheduled inspection
Start date: 2018-12-17, end date: 2018-12-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: and this inspection is carried out in accordance with the inspection program received by the developer's representative, the Administration of the Frolovsky Municipal District of the Volgograd Region, in order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation, legislation of the Russian Federation in the field of environmental protection, fire safety and sanitary and epidemiological welfare of the population, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices used energy resources, including technical regulations and project documentation b the purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation The subject of this audit is compliance with mandatory requirements regarding a compliance of construction works, their results and applied building materials with the requirements of project documentation b availability of building permits c meeting the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation