# 762005171465
Unscheduled inspection
Start date: 2020-10-09, end date: 2020-10-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Based on the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of the design documentation7 The subject of this audit is to comply with mandatory requirements
# 762005202904
Unscheduled inspection
Start date: 2020-10-29, end date: 2020-11-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Proverka provoditsya s celyu na osnovanii izvescheniya ob okonchanii stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva 1513 ot 21102020 gZadachami nastoyaschei proverki yavlyayutsya opredelenie sootvetstviya postroennogo obekta kapitalnogo stroitelstva trebovaniyam proektnoi dokumentacii7 Predmetom nastoyaschei proverki yavlyaetsyasoblyudenie obyazatelnyh trebovanii
# 762004439127
Unscheduled inspection
Start date: 2020-06-29, end date: 2020-06-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of project documentation7 The subject of this audit is compliance with mandatory requirements
# 762004367352
Unscheduled inspection
Start date: 2020-03-26, end date: 2020-03-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This inspection is carried out in order to determine, based on the verification program, the objectives of this inspection are to determine whether the work performed during the construction of a capital construction facility meets the requirements of the design documentation
# 761904091160
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation
# 761903000344
Unscheduled inspection
Start date: 2019-08-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 761902844776
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements