# 062101512389
Unscheduled inspection
Start date: 2021-12-20, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Ingushetiya
Purpose of inspection:
# 062101512296
Unscheduled inspection
Start date: 2021-12-20, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Ingushetiya
Purpose of inspection: Goal
Planned, according to the inspection program
Task
Verification of compliance of work performed and construction materials used during the construction, reconstruction of a capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for energy resources used
Subject
1 compliance with the conformity of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation
2 compliance with the requirement of a building permit
3 compliance with the requirements established by Parts 2 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation
4 compliance with the requirements established by part 4 of Article 52 of the Urban Planning Code of the Russian Federation to ensure the conservation of a capital construction facility; requirements for the procedure for carrying out construction control established by the Urban Planning Code of the Russian Federation and other regulatory legal acts