# 61160700088151
Unscheduled inspection
Start date: 2016-08-11, end date: 2016-08-15, duration: —
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This audit is conducted in order to comply with clause 7 of the Audit Program in case 011484. The objectives of this audit are to prevent identify and suppress violations of urban planning legislation committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor. The purpose of this audit is to verify the compliance of the work performed and the construction materials used. materials in the process of construction reconstruction of a capital construction facility, as well as the results of such work, meet the requirements of technical regulations and project documentation