Found 7 inspections:

# 742004472207
Unscheduled inspection
Start date: 2020-08-03, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 742004475928
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-14, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of work on the Warehouse of finished products, installation of technological equipment, installation of metal structures, installation of internal engineering networks, installation of integrated electrical equipment during the Pumping station, installation of electricity and electric lighting during the work, Landscaping during the work and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 152 and 153 of Article 48 of this Code of the project documentation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities which energy efficiency requirements do not apply to and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 742004404992
Unscheduled inspection
Start date: 2020-05-18, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 742004235386
Unscheduled inspection
Start date: 2020-02-10, end date: —, duration:
Authority:
Purpose of inspection:


# 741904044758
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-17, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of work on the Warehouse of finished products with the installation of a membrane roof in the process of work, the installation of a monolithic floor slab in the process of work, the installation of internal engineering networks in the process of work, the installation of external on-site networks and structures in the process of work, the Administrative building, the installation of external on-site networks and structures in the process of work, the pumping station, and construction work in the process of work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model if the formation and maintenance of information models are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for energy resources used2 The availability of a construction permit3 Compliance with the requirements of HH 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 74160701057457
Unscheduled inspection
Start date: 2016-11-01, end date: 2016-11-08, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po zaversheniyu elektroobespecheniya i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2Nalichie razresheniya na stroitelstvo3Vypolnenie trebovanii chch 23 st52 Gradostroitelnogo kodeksa RF


# 74160700973386
Unscheduled inspection
Start date: 2016-10-17, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.