# 721903921629
Unscheduled inspection
Start date: 2019-10-29, end date: 2019-11-25, duration: —
Authority: Gosudarstvennaya inspekciya truda v Tyumenskoi oblasti
Purpose of inspection: compliance with labor laws
# 72160701269223
Unscheduled inspection
Start date: 2016-12-08, end date: 2016-12-30, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notification dated 30112016 bn on the completion of construction reconstruction of a capital construction facility, verification of compliance of work performed and construction materials used during construction as well as the results of such work with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used during construction the capital construction facility "Public housing complex on Muravlenko St. in Tyumen, the third stage of construction" located at the address Tyumen region, Tyumen, Muravlenko St.
# 72160701098717
Unscheduled inspection
Start date: 2016-11-07, end date: 2016-12-02, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Verification of the elimination of violations according to the order of 14102016 116516ts on the basis of the notice on the elimination of violations during the construction of the reconstruction of the capital construction facility of 26102016 Verification of compliance of the work and the construction materials used during construction as well as the results of such work with the requirements of technical regulations other regulatory legal acts of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with metering devices the energy resources used in the construction of the capital construction facility "Public housing complex on Muravlenko St. in Tyumen, the third stage of construction" located at the address Tyumen region, Tyumen, Muravlenko St.
# 72160700792499
Unscheduled inspection
Start date: 2016-09-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72160700028494
Unscheduled inspection
Start date: 2016-08-18, end date: 2016-08-31, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notice on the completion dates of works subject to verification during the construction reconstruction of a capital construction facility dated 27072016 Verification of compliance of the work and the construction materials used during construction as well as the results of such work with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices used energy resources during the construction of the capital construction facility "Public housing complex on Muravlenko Street in Tyumen, the third stage of construction" located at the address Tyumen region, Tyumen, Muravlenko Street