# 241903912959
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-12-02, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation
# 24190803466265
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-28, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of checking the implementation of regional state construction supervision during the reconstruction of the specified capital construction facility in connection with the onset of completion dates that are subject to verification in accordance with the approved program of 21052019 conducting inspections during the reconstruction of the capital construction facility Verification tasks prevention detection and suppression of violations of legislation on urban development, including technical regulations and project documentation Subject of verification verification compliance of the work and construction materials used in the process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used checking the availability of a certificate of admission to the types of work on reconstruction of the capital construction facility that affect the safety of the facility capital construction
# 24190803417360
Unscheduled inspection
Start date: 2019-05-17, end date: 2019-06-14, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to carry out regional state construction supervision during the reconstruction of the specified capital construction facility on the basis of the received notification 71 dated 07052019 on the beginning of the reconstruction of the capital construction facility The tasks of the audit are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and project documentation The subject of the audit is to verify the compliance of the work and the construction materials used during the reconstruction of the facility capital construction, as well as the results of such work, the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, verification of the availability of a permit for reconstruction
# 24170802519919
Unscheduled inspection
Start date: 2017-10-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 24150601410820
Unscheduled inspection
Start date: 2015-11-13, end date: 2015-12-11, duration: —
Authority: Gosudarstvennaya inspekciya truda v Krasnoyarskom krae
Purpose of inspection: supervision of compliance with labor legislation and other regulatory legal acts containing labor law norms