# 272100466617
Unscheduled inspection
Start date: 2021-08-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 272000242281
Unscheduled inspection
Start date: 2021-05-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection:
# 272000035348
Unscheduled inspection
Start date: 2021-02-26, end date: 2021-02-02, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out for the purpose of carrying out regional state construction supervision on the basis of the notice on the completion dates of the works to be inspected dated 02/19/2021 No. 119/4 (ex. dated 02/19/2021 No. 630).
The objectives of this audit are: prevention, detection, and suppression of violations of current legislation on urban development and project documentation.
The subject of this audit is to verify the compliance of the work performed and the construction materials used during the construction of the Facility, as well as the results of such work with the requirements of the design documentation.
# 272005295234
Unscheduled inspection
Start date: 2020-12-28, end date: 2021-02-02, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out for the purpose of implementing regional state construction supervision on the basis of the notice of completion of the capital construction facility dated 25122020 194 bx dated 25122020 6497the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility as well as the results of such work meet the requirements of the project documentation
# 272005236342
Unscheduled inspection
Start date: 2020-11-27, end date: 2020-12-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out for the purpose of implementing regional state construction supervision on the basis of the notice of completion of the capital construction facility dated 13112020 bn BX dated 16112020 5742the objectives of this inspection are the prevention detection suppression of violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility as well as the results of such work meet the requirements of the project documentation
# 272005190873
Unscheduled inspection
Start date: 2020-10-27, end date: 2020-11-24, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 12102020 1154 bx dated 13102020 5183 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility as well as the results of such work according to the requirements of the project documentation
# 272004428191
Unscheduled inspection
Start date: 2020-06-10, end date: 2020-07-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 01062020 bn bx dated 01062020 2734 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility as well as the results of such work according to the requirements of the project documentation
# 272004322839
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection from 20022020 bn bx from 21022020 873 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility as well as the results of such work according to the requirements of the project documentation
# 272004216985
Unscheduled inspection
Start date: 2020-01-24, end date: 2020-02-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 15012020 bn BX dated 15012020 96 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility and also, the results of such work meet the requirements of the project documentation
# 271904118194
Unscheduled inspection
Start date: 2019-12-13, end date: 2020-01-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the notice of completion of the capital construction facility dated 06122019 bn VH dated 06122019 5822the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe subject of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility as well as the results of such work meet the requirements of the project documentation
# 271903938918
Unscheduled inspection
Start date: 2019-11-07, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection:
# 271903730114
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program of the Facility from 05022018the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentationthe purpose of this inspection is to verify the compliance of completed works and applied building materials during the construction of the Facility as well as the results of such work with the requirements of the project documentation
# 271902489743
Unscheduled inspection
Start date: 2019-02-15, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection:
# 271802217755
Unscheduled inspection
Start date: 2018-12-06, end date: 2019-01-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this audit is conducted for the purpose of implementing regional state construction supervision on the basis of the notice of completion of the capital construction facility dated November 28, 2018 2 vx 5928 dated November 28, 2018 The purpose of this audit is to prevent identify and suppress violations of current legislation on urban development activities, including project documentation. The subject of this audit is to verify the compliance of work and the application of construction materials during the construction of the Facility as well as the results of such work meet the requirements of the project documentation
# 271801918032
Unscheduled inspection
Start date: 2018-10-10, end date: 2018-11-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 02102018 bn vh dated 02102018 4837 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development and project documentation The subject of this inspection is to verify the compliance of completed works and applied building materials during construction and reconstruction The object as well as the results of such work meet the requirements of the project documentation
# 271800753781
Unscheduled inspection
Start date: 2018-09-04, end date: 2018-10-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision in connection with the expiration of the deadline for the fulfillment by RacioPolis LLC of the regulation dated 23072018 C051518 on the elimination of violations during the reconstruction of a capital construction facility issued by the state construction supervision authority The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentation. verification is the verification of the fulfillment of the Prescription
# 271800589671
Unscheduled inspection
Start date: 2018-07-27, end date: 2017-08-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is being conducted for the purpose of implementing regional state construction supervision on the basis of the notice dated July 20, 2018 on the completion dates of works subject to inspection bx 3576 dated 23072018. The purpose of this inspection is to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentation. The subject of this inspection is to verify the compliance of the work and the construction materials used during the reconstruction of the Facility, as well as the results of such work, meet the requirements of the technical regulations of the project documentation
# 271800483654
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-07-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision based on the appeal of citizen Klimenko YU dated 11062018 to the e-mail address of the Government of the Khabarovsk Territory about the construction of an Object with violations of the requirements of technical regulations of project documentation that pose a threat of harm to human life health property of individuals The objectives of this inspection are to prevent detect and suppress violations of current legislation on urban planning activities, including technical regulations and project documentation
# 271800387687
Unscheduled inspection
Start date: 2018-05-23, end date: 2018-06-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision in connection with the expiration of the deadline for the fulfillment by RacioPolis LLC of the regulation dated 27042018 C04142018 on the elimination of violations during the reconstruction of a capital construction facility issued by the state construction supervision authority The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentation. verification is the verification of the fulfillment of the Prescription
# 271800240826
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 21032018 bn bx dated 22032018 1162 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentation. The subject of the inspection is to verify the conformity of completed works and applied building materials during the construction of the Facility as well as the results of such work, the requirements of the technical regulations of the project documentation
# 271800013968
Unscheduled inspection
Start date: 2018-01-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 27170802960790
Unscheduled inspection
Start date: 2017-12-20, end date: 2017-12-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this audit is conducted in order to verify the facts set out in reasoned submission 182317 dated November 30, 2017 in the implementation of regional state control supervision in the field of shared-equity construction of apartment buildings and or other real estate objects, the objectives of this audit are to prevent identify and suppress violations of current legislation in the field of shared-equity construction of apartment buildings and or other real estate objects and ensure the protection of human rights The subject of this audit is compliance with the mandatory requirements established by the Federal Law of 30122004 214 FZ On Participation in the Shared Construction of Apartment Buildings and Other Real Estate Objects and on Amendments to Certain Legislative acts of the Russian Federation and other regulatory legal acts of the Russian Federation adopted in accordance with it.
# 27170802887710
Unscheduled inspection
Start date: 2017-11-27, end date: 2017-12-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection dated 15112017 bn BX dated 15112017 5581the objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentationthe subject of this inspection is to verify the conformity of completed works and applied building materials in during the construction reconstruction of the Facility, as well as the results of such work, the requirements of the technical regulations of the project documentation
# 27170701694487
Unscheduled inspection
Start date: 2017-06-19, end date: 2017-07-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this audit is conducted for the purpose of implementing regional state construction supervision on the basis of a notice from Eurasian Holding Company LLC on the completion dates of works subject to verification dated 02062017 bx 2604 dated 02062017the objectives of this audit are to prevent identify and suppress violations of current legislation on urban development, including technical regulations and design documentationthe subject of this audit is to verify the compliance of the work performed and the applicable construction materials during the construction of the Facility as well as the results of such work meet the requirements of the technical regulations of the project documentation
# 27160701157767
Unscheduled inspection
Start date: 2016-11-28, end date: 2016-12-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out for the purpose of implementing regional state construction supervision on the basis of a notice on the completion dates of works subject to inspection during the construction of a capital construction facility dated 17112016 bn from Eurasian Holding Company LLC No. 4725 dated 17112016the purpose of this inspection is to monitor compliance by construction participants with legislation on urban development activities. The purpose of this inspection is to verify the compliance of work performed and construction materials used materials during the construction of the Facility, as well as the results of such work, meet the requirements of the technical regulations of the project documentation
# 27160700056787
Unscheduled inspection
Start date: 2016-08-25, end date: 2016-09-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: The purpose of the inspection is to carry out regional state construction supervision based on the inspection program dated March 15, 2016The purpose of the inspection is to monitor compliance by construction participants with legislation on urban development