Found 4 inspections:

# 242100032016
Unscheduled inspection
Start date: 2021-02-26, end date: 2021-03-26, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Krasnoyarskom krae
Purpose of inspection: Osuschestvlenie federalnogo gosudarstvennogo nadzora za soblyudeniem yuridicheskim licom ili individualnym predprinimatelem obyazatelnyh trebovanii trudovogo zakonodatelstva i inyh normativnyh pravovyh aktov, soderzhaschih normy trudovogo prava; pismennoe obraschenie rabotnika Zontovoi YU.V. № 24/7-1163-21-OB ot 12.02.2021g.


# 242100000512
Unscheduled inspection
Start date: 2021-02-15, end date: —, duration:
Authority:
Purpose of inspection:


# 001904212486
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-27, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu proverki vypolneniya meropriyatii predusmotrennyh punktami 14 67 11 13 1720 2226 3334 4043 45 4851 5357 ranee vydannogo predpisaniya ot 15082019 11150T srok ispolneniya kotorogo istekaet 29112019Zadachei nastoyaschei proverki yavlyaetsya proverka fakticheskogo vypolneniya obyazatelnyh trebovanii ukazannyh v predpisanii ot 15082019 11150T v ustanovlennye sroki Predmetom nastoyaschei proverki yavlyaetsya vypolnenie punktov 14 67 11 13 1720 2226 3334 4043 45 4851 5357 predpisaniya ot 15082019 11150T organa gosudarstvennogo kontrolya nadzora


# 001902892915
Unscheduled inspection
Start date: 2019-07-22, end date: 2019-08-16, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the progress of preparation of heat supply facilities for operation in the autumn winter period 20192020 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 261 and the instructions of the Government of the Russian Federation dated 19062019 VMP95084 "On monitoring the progress of preparation and assessment of the readiness of heat supply facilities for operation in the autumn winter period 20192020"The objectives of this audit are to verify the progress of the preparation of heat supply facilities for operation in the autumn winter period of 2019-2020. The purpose of this audit is to comply with the requirements of Federal laws and other normative legal acts of the Russian Federation when preparing for the autumn winter period of 20192020


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.