# 14170801950126
Unscheduled inspection
Start date: 2017-09-07, end date: 2017-10-04, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: verification of the completed capital construction facility for a compliance of the constructed capital construction facility with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation b elimination by the developer by the technical customer by the person carrying out construction of all violations of compliance of the performed works with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation for the execution of executive documentation related to the performance of all construction work as well as the use of building materials and products According to Notice 1 dated 21082017 No. 312389 dated 22082017 on the completion of construction of the Department of Gosstroizhilnadzor of the Russian Federation
# 14170802761537
Unscheduled inspection
Start date: 2017-08-25, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701793813
Unscheduled inspection
Start date: 2017-07-14, end date: 2017-08-10, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation1, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor, to ensure that the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, comply with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation the availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by the developer or the technical customer on the basis of the contract of the natural or legal person According to the program of inspections