# 142100494350
Unscheduled inspection
Start date: 2021-08-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142100302487
Unscheduled inspection
Start date: 2021-05-31, end date: —, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Respublike Saha (YAkutiya)
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms.
# 142004445231
Unscheduled inspection
Start date: 2020-07-10, end date: 2020-07-22, duration: 9
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142004275026
Unscheduled inspection
Start date: 2020-02-19, end date: 2020-03-05, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142004206422
Unscheduled inspection
Start date: 2020-01-21, end date: 2020-02-17, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141904036410
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-16, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 141904206213
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-12-12, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141903647874
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-10-07, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141902928334
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-16, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, of compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation in including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Development Code of the Russian Federation to the inspection program
# 141902791639
Unscheduled inspection
Start date: 2019-06-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141902537008
Unscheduled inspection
Start date: 2019-03-06, end date: 2019-03-19, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii 1 sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 nalichiya razresheniya na stroitelstvo 3 vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 6 stati 52 Gradostroitelnogo Kodeksa RF Po programme proverok «Monitoring temperatury gruntov osnovaniya i nablyudeniya za osadkami osnovaniya zdaniya i sooruzhenii Konstrukcii nulevogo cikla Plita cokolnogo perekrytiya Metallokarkas Kladochnye raboty Oblicovka «sendvichpanelei» Prochie raboty Razrabotka PPR PPR geodezicheskie ili tehnologicheskie karty Raboty po osuschestvleniyu stroitelnogo kontrolya i organizacii stroitelnogo proizvodstva»
# 141802214789
Unscheduled inspection
Start date: 2018-12-14, end date: 2018-12-28, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 141802446978
Unscheduled inspection
Start date: 2018-11-21, end date: 2018-12-18, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor) 1 compliance of the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 the fulfillment of the requirements established by parts 2 3 and 31 of Article 52 of this Code
# 141802494073
Unscheduled inspection
Start date: 2018-10-08, end date: 2018-11-02, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii 1sootvetstvie postroennogo obekta kapitalnogo stroitelstva trebovaniyam tehnicheskih reglamentov norm i pravil inyh normativnyh pravovyh aktov i proektnoi dokumentacii 2ustranenie zastroischikom tehnicheskim zakazchikom licom osuschestvlyayuschim stroitelstvo vyyavlennyh pri provedenii stroitelnogo kontrolya i osuschestvlenii gosudarstvennogo nadzora vseh narushenii sootvetstviya vypolnennyh rabot trebovaniyam tehnicheskih reglamentov norm i pravil inyh normativnyh pravovyh aktov i proektnoi dokumentacii 3oformlenie ispolnitelnoi dokumentacii svyazannoi s vypolneniem vseh rabot po stroitelstvu a takzhe primeneniem stroitelnyh materialov izdelii
# 141802446962
Unscheduled inspection
Start date: 2018-10-08, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170801931584
Unscheduled inspection
Start date: 2017-09-05, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701861472
Unscheduled inspection
Start date: 2017-07-27, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701861471
Unscheduled inspection
Start date: 2017-07-27, end date: 2017-08-09, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya1 sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 nalichie razresheniya na stroitelstvo3vypolnenie trebovanii chastei 236 stati 52 Gradostroitelnogo kodeksa RF nalichie svidetelstva o dopuske k rabotam po stroitelstvu rekonstrukcii kotorye okazyvayut vliyanie na bezopasnost obektov kapitalnogo stroitelstva v tom chisle svidetelstva o dopuske k rabotam po organizacii stroitelstvo v sluchae privlecheniya zastroischikom ili tehnicheskim zakazchikom na osnovanii dogovora fizicheskogo ili yuridicheskogo lica4 po programme proverok po predpisaniyu
# 14170701861418
Unscheduled inspection
Start date: 2017-07-27, end date: 2017-08-09, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the conformity of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work for the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or a legal person4 according to the order
# 14170701861394
Unscheduled inspection
Start date: 2017-07-20, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701664847
Unscheduled inspection
Start date: 2017-06-06, end date: 2017-06-20, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, and the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor. The subject of this audit is the conformity of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such requirements of the technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction and reconstruction work that affect the safety of capital construction facilities, including a certificate of admission to work for the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or a legal person4 according to the inspection program