Found 16 inspections:

# 242100988953
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility, in connection with the onset of completion dates, which are subject to verification in accordance with the approved program of 05/19/2021 inspections during the construction of the capital construction facility.; The objectives of this audit are to prevent, identify and suppress violations of legislation on urban development, including project documentation. 7. The subject of this audit is: 7.1. Verification of compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the design documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Planning Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation); 7.2. Requirements for a construction permit, as well as the parameters of a capital construction facility under construction or reconstruction specified in the construction permit; 7.3. Requirements established by Parts 2 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; 7.4. Requirements to the construction control procedure established by the Urban Planning Code of the Russian Federation and other regulatory legal acts.


# 242100314037
Unscheduled inspection
Start date: 2021-08-16, end date: —, duration: 12
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility, in connection with the onset of completion dates, which are subject to verification in accordance with the approved program of 05/19/2021 inspections during the construction of the capital construction facility.; The objectives of this audit are to prevent, identify and suppress violations of legislation on urban development, including project documentation. 7. The subject of this audit is: 7.1. Verification of compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the design documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Development Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Development Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities, which are not subject to energy efficiency requirements) and equipment requirements of the capital construction facility metering devices for used energy resources; 7.2. Meeting the requirements set out in Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; 7.3. Verification of the construction permit.


# 002005282560
Unscheduled inspection
Start date: 2020-12-21, end date: 2021-01-25, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the implementation of the measures provided for in paragraphs 17112020 093763 previously issued to the person being checked on the elimination of identified violations of mandatory requirements in connection with the received petition 07122020 401 bx 36146479 08122020 The purpose of this inspection is to establish the fact of elimination of previously identified violations of the regulation 17112020 093763 The subject of this inspection is to verify compliance with the regulation of the state construction agency supervision from 17112020 093763


# 242004460981
Unscheduled inspection
Start date: 2020-08-03, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 242004420611
Unscheduled inspection
Start date: 2020-06-01, end date: 2020-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program from 27032020 for inspections during the construction of a capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including project documentation7 The subject of this audit is71 Verification of the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation If the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used72 Compliance with the requirements set out in Parts 2 3 and 31 Article 52 of the Urban Planning Code of the Russian Federation73 Verification of a building permit


# 242004471356
Unscheduled inspection
Start date: 2020-06-30, end date: —, duration:
Authority:
Purpose of inspection:


# 241903641040
Unscheduled inspection
Start date: 2019-10-04, end date: —, duration:
Authority:
Purpose of inspection:


# 24190803485252
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-27, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of checking the implementation of regional state construction supervision during the construction of the specified capital construction facility in connection with the deadline for completion of work that is subject to verification in accordance with the approved program of 16072019 inspections during the construction of the capital construction facility The tasks of the inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation The subject of the inspection is verification compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used. verification of the certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the facility capital construction


# 241800616271
Unscheduled inspection
Start date: 2018-08-14, end date: 2018-08-27, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the instruction dated 29062018 1883DPO on the elimination of identified violations at the specified capital construction facility, which expires on 13082018. The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241800391982
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 24102017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 24170802908227
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 24102017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation7 The subject of this audit is71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used72 Compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code Of the Russian Federation73 Checking the availability of a building permit


# 24170802576733
Unscheduled inspection
Start date: 2017-09-20, end date: 2017-09-22, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued instruction from 31082017 3316DPO on the elimination of identified violations at the specified capital construction facility in connection with the notification received from 12092017 bx 94 on the elimination of violations before the expiration of the period specified in the prescriptionthe objectives of this inspection are to establish the elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures


# 24170802576714
Unscheduled inspection
Start date: 2017-09-20, end date: 2017-09-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued instruction from 04092017 3547DPO on the elimination of identified violations at the specified capital construction facility in connection with the notification received from 12092017 vx 95 on the elimination of violations before the expiration of the period specified in the prescriptionthe objectives of this inspection are to establish the elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures


# 24170701870510
Unscheduled inspection
Start date: 2017-08-29, end date: 2017-09-11, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the previously issued to the person being audited order dated 19072017 2696DPO on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 28082017the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the body carrying out Regional State construction supervision


# 24170701831887
Unscheduled inspection
Start date: 2017-08-04, end date: 2017-08-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 31052017 inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation7 The subject of this audit is71 Checking the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources 72 Checking the availability of a construction permit 73 Checking the availability of a certificate of admission to the types of works on the construction of a capital construction facility that have an impact on the safety of the capital construction facility


# 24170701716987
Unscheduled inspection
Start date: 2017-07-03, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.