# 161801876578
Unscheduled inspection
Start date: 2018-10-02, end date: 2018-10-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of compliance of the eliminated violations with the requirements of technical regulations, design documentation, other normative acts, norms and rules, as well as for the purpose of drawing up an act on the elimination of violations on the basis of the notification received by the Inspection from 13092018 6633 on the elimination of violations during the construction reconstruction of a capital construction facility that were ordered to be eliminated within the time limit established by the order from 06062018 121905101 to 15092018 prevention as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with the instructions of state control bodies, supervision of municipal control bodies
# 161801876807
Unscheduled inspection
Start date: 2018-10-05, end date: 2018-10-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of compliance of the performed works of the applied building materials during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of verification of the completed construction facility in accordance with the notification received by the Inspection from 26092018 7060 on completion of construction of a capital construction facility prevention as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer with the requirements of mandatory requirements and or requirements established by municipal legal acts
# 161800423019
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-06-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with with the inspection program dated 28112017 case 121120170133 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800074665
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-03-07, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: 6 To establish that This audit is carried out in order to protect the rights and interests of employees the basis of paragraph 4 h 7 of Article 360 of the Labor Code memo dated 06022018 When establishing the objectives of the audit, the following information is indicated and in the case of a scheduled audit, a link to the approved annual plan for scheduled inspections details of the checklist list of control questions if during the scheduled audit a checklist list of control questions can be used b in the case of an unscheduled inspection, the details of an order previously issued to the person being checked to eliminate the detected violation, the deadline for which has expired, the details of an application from a legal entity or an individual entrepreneur for granting the legal status of a special permit license for the right to carry out certain types of activities or permission to coordinate other legally significant actions if the conduct the relevant unscheduled inspection of a legal entity of an individual entrepreneur is provided for by the rules for granting the legal status of a special permit license issuance of a permit approval of the details of appeals and applications of citizens of legal entities of individual entrepreneurs received by the state control bodies supervision bodies of municipal control, as well as information on information received from state authorities and local self-government bodies
# 161800017995
Unscheduled inspection
Start date: 2018-01-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170802928791
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of compliance of the construction materials used in the construction of a capital construction facility with the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 28112017 case 121120170133 prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with mandatory requirements and or requirements established by municipal legal acts performed during the construction of a capital construction facility