Found 11 inspections:

# 632101410950
Unscheduled inspection
Start date: 2021-12-03, end date: —, duration:
Authority:
Purpose of inspection:


# 632100433486
Unscheduled inspection
Start date: 2021-08-17, end date: —, duration:
Authority:
Purpose of inspection:


# 632100343982
Unscheduled inspection
Start date: 2021-07-14, end date: —, duration:
Authority:
Purpose of inspection:


# 632100311769
Unscheduled inspection
Start date: 2021-07-01, end date: —, duration:
Authority:
Purpose of inspection:


# 632100040293
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-03-31, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.


# 632005245782
Unscheduled inspection
Start date: 2020-12-01, end date: —, duration:
Authority:
Purpose of inspection:


# 632005245777
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-28, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 632005162086
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-10-28, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 632004478472
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-28, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 632004423123
Unscheduled inspection
Start date: 2020-06-08, end date: —, duration:
Authority:
Purpose of inspection:


# 632004280148
Unscheduled inspection
Start date: 2020-02-14, end date: 2020-02-28, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.