# 742100108072
Unscheduled inspection
Start date: 2021-04-07, end date: 2021-04-13, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the installation of foundations and building materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of the Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices used energy resources. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 742005231562
Unscheduled inspection
Start date: 2020-11-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742005145659
Unscheduled inspection
Start date: 2020-10-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742004442545
Unscheduled inspection
Start date: 2020-06-30, end date: —, duration: —
Authority: —
Purpose of inspection: