# 772100267146
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-30, duration: 17
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772004209479
Unscheduled inspection
Start date: 2020-01-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771904065395
Unscheduled inspection
Start date: 2019-12-06, end date: 2019-12-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 771903950547
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771903692720
Unscheduled inspection
Start date: 2019-09-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803412150
Unscheduled inspection
Start date: 2019-05-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802760457
Unscheduled inspection
Start date: 2017-10-17, end date: 2017-10-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701884126
Unscheduled inspection
Start date: 2017-09-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701681821
Unscheduled inspection
Start date: 2017-06-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701443363
Unscheduled inspection
Start date: 2017-03-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701135728
Unscheduled inspection
Start date: 2016-11-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160601751144
Unscheduled inspection
Start date: 2016-07-29, end date: 2016-07-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniipreduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiproverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 661816 ot 28062016