# 002105316977
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-28, duration: 4
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to monitor the implementation of Regulation No. 116-G dated March 16, 2020./3.3-20/ Z-07.
The objectives of this audit are:
to monitor the measures taken
by the legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development activities during the construction and reconstruction of a capital construction facility.;
taking measures to eliminate violations of mandatory requirements
(if they are identified) and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.
The subject of the audit is the fulfillment of the instructions of the state control (supervision) body
# 001902951526
Unscheduled inspection
Start date: 2019-08-19, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902539300
Unscheduled inspection
Start date: 2019-02-21, end date: 2019-02-22, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to control the fulfillment by Parallax LLC of a previously issued instruction. The purpose of this check is to establish the facts of Parallax LLC's failure to comply with the above-mentioned instruction. The subject of this check is Parallax LLC's fulfillment of the instruction to eliminate the identified violations
# 162105317064
Unscheduled inspection
Start date: 2021-01-27, end date: 2021-01-29, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, and other regulations (norms and rules), as well as to draw up an act on the elimination of violations, based on the notice received by the Inspectorate dated 12/30/2020 No. 15317; 12/30/2020 No. 15309 on the elimination of violations during construction, reconstruction of a capital construction facility, which were ordered to be eliminated within the time limit set by the order from 18.12.2020 №12-12/1218-02; 18.12.2020 №12-12/1218-01, until 29.01.2021
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is (select the appropriate one):
compliance with the regulations of state control (supervision) bodies, municipal control bodies;
# 002105316977
Unscheduled inspection
Start date: 2021-01-25, end date: 2021-01-28, duration: 4
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to monitor the implementation of Regulation No. 116-G dated March 16, 2020./3.3-20/ Z-07.
The objectives of this audit are:
to monitor the measures taken
by the legal entity to comply with the regulations and comply with the mandatory requirements of legislation on urban development activities during the construction and reconstruction of a capital construction facility.;
taking measures to eliminate violations of mandatory requirements
(if they are identified) and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.
The subject of the audit is the fulfillment of the instructions of the state control (supervision) body
# 162005253886
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-02, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the instruction dated 27102020 1212104201, the deadline for which expired on 23112020, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory documents performed during the construction of a capital construction facility. The purpose of this audit is to comply with the requirements of state control bodies, supervision bodies, and municipal control bodies.
# 162005253797
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-02, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 23112020 13064 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which were ordered to be eliminated within the time limit set by the order from 23102020 1212101101 to 23112020 and the expiration date of the order from 23102020 1212101101, the deadline for which expired on 23112020the tasks of this audit are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, violations of compliance with the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentation. Documentationthe subject of this audit is to comply with the instructions of state control bodies, supervision bodies, and municipal control bodies.
# 162005259391
Unscheduled inspection
Start date: 2020-12-07, end date: 2020-12-18, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 250-52020 case 120420200033the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations and other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer with the requirements of technical regulations and other regulatory legal acts and project documentation. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts. acts
# 162005259278
Unscheduled inspection
Start date: 2020-12-07, end date: 2020-12-18, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 260-52020 case 120420200031the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations and other regulatory legal acts and project documentation carried out by the developer, the customer, or the person carrying out reconstruction on the basis of a contract with the developer or the customer with the requirements of technical regulations and other regulatory legal acts and project documentation. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts. acts
# 162005246404
Unscheduled inspection
Start date: 2020-12-03, end date: 2020-12-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 22052020 case 120420200032the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005267265
Unscheduled inspection
Start date: 2020-12-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162005238813
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-11-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 17092020 1212088001, the deadline for which expired on 19102020 17092020 1212088002, the deadline for which expired on 19102020 and drawing up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer performed during the construction of a capital construction facility. The purpose of this audit is to select the required compliance with the requirements of state control bodies, supervision bodies, and municipal control bodies.
# 162005179966
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 260-52020 case 120420200031 aims to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162005178388
Unscheduled inspection
Start date: 2020-10-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004626429
Unscheduled inspection
Start date: 2020-08-05, end date: 2020-09-01, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms On behalf of Deputy Prime Minister of the Russian Federation Tagolikova dated December 27, 2019 TGP1211486 reasoned submission 16327020PV dated 04082020
# 162004443627
Unscheduled inspection
Start date: 2020-07-02, end date: 2020-07-03, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 250-52020 case 120420200033 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004443617
Unscheduled inspection
Start date: 2020-07-02, end date: 2020-07-03, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 260-52020 case 120420200031 aims to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004461991
Unscheduled inspection
Start date: 2020-07-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004461971
Unscheduled inspection
Start date: 2020-07-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004294409
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-02-17, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to control the fulfillment by Parallax LLC of a previously issued instruction. The purpose of this check is to establish the facts of Parallax LLC's failure to comply with the above-mentioned instruction. The subject of this check is Parallax LLC's fulfillment of the instruction to eliminate the identified violations
# 162004161651
Unscheduled inspection
Start date: 2020-01-16, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004161646
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-01-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 25/12/2019 1212/128302, the deadline for which expired on 26/122019 25112019 1212/128301, the deadline for which expired on 26/122019, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer performed during the construction of the facility The subject of this audit is the fulfillment of the requirements of the state control bodies supervision of municipal control bodies and the requirements of the technical regulations of other regulatory legal acts and project documentation.
# 162004161638
Unscheduled inspection
Start date: 2020-01-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903976514
Unscheduled inspection
Start date: 2019-11-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903976431
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-11-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 22072019 case 121120190084the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161903976377
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-11-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 22072019 case 121120190083the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161903907463
Unscheduled inspection
Start date: 2019-10-25, end date: 2019-11-22, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: The purpose of the audit is to protect the rights and interests of employees on the basis of ch7 st360 of the Labor Code of the Russian Federation Tasks of verification ensuring compliance with and protection of labor rights and freedoms of citizens ensuring compliance by the employer with labor legislation and other regulatory legal acts containing norms of labor law Subject to verification compliance with mandatory requirements or requirements established by municipal legal acts
# 161903855828
Unscheduled inspection
Start date: 2019-10-17, end date: 2019-10-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of compliance with the order dated 04092019 1212093101, the deadline for which expired on 04102019, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and prevent violations of compliance by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory documents performed during the construction of a capital construction facility. legal acts and project documentationthe subject of this audit is to select the necessary fulfillment of the instructions of the state control bodies, supervision bodies of municipal control
# 161903855685
Unscheduled inspection
Start date: 2019-10-17, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903855888
Unscheduled inspection
Start date: 2019-10-17, end date: 2019-10-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of compliance with the order dated 04092019 1212093301, the deadline for which expired on 04102019, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and prevent violations of compliance by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory documents performed during the construction of a capital construction facility. legal acts and project documentationthe subject of this audit is to select the necessary fulfillment of the instructions of the state control bodies, supervision bodies of municipal control
# 001902951526
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-08-20, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this check is carried out in order to control the execution by a legal entity of a previously issued prescription. The task of this check is to eliminate the facts of compliance with the previously issued prescription. The subject of this check is the execution of an instruction to eliminate identified violations
# 161903002727
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-09-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 22072019 case 121120190084the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161903002676
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-09-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 22072019 case 121120190085the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161903002573
Unscheduled inspection
Start date: 2019-08-28, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 001902539300
Unscheduled inspection
Start date: 2019-02-21, end date: 2019-02-22, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This check is carried out in order to control the fulfillment by Parallax LLC of a previously issued instruction. The purpose of this check is to establish the facts of Parallax LLC's failure to comply with the above-mentioned instruction. The subject of this check is Parallax LLC's fulfillment of the instruction to eliminate the identified violations
# 77180803296395
Unscheduled inspection
Start date: 2018-12-11, end date: 2018-12-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 161802008964
Unscheduled inspection
Start date: 2018-10-17, end date: 2018-11-15, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: The objectives of this audit are to ensure that the labor rights and freedoms of citizens are respected and protected, and to ensure that the employer complies with labor laws and other regulatory legal acts containing labor law norms. 7 The subject of this audit is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts. The information contained in the notification of the commencement of certain types of business activities with mandatory requirements. contained in the application and documents of a legal entity or individual entrepreneur for granting the legal status of a special permit license for the right to carry out certain types of activities or authorization approval for other legally significant actions if the conduct of an appropriate unscheduled inspection of a legal entity individual entrepreneur is provided for by the rules for granting the legal status of a special permit license issuance of a permit approval of mandatory requirements as well as the data of authorized legal entities and individual entrepreneurs contained in the unified state register of legal entities, the unified state register of individual entrepreneurs and other federal information resources, compliance with the instructions of state control bodies, supervision bodies, municipal control bodies, measures to prevent harm to the life and health of citizens, harm to animals, plants, the environment, to prevent the occurrence of natural and man-made emergencies, to ensure the safety of the state, to eliminate the consequences of causing Such harm
# 77180803193184
Unscheduled inspection
Start date: 2018-08-03, end date: 2018-08-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803176135
Unscheduled inspection
Start date: 2018-07-10, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803125735
Unscheduled inspection
Start date: 2018-04-20, end date: 2018-04-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803108038
Unscheduled inspection
Start date: 2018-03-22, end date: 2018-03-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803058722
Unscheduled inspection
Start date: 2018-01-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802893200
Unscheduled inspection
Start date: 2017-11-23, end date: 2017-11-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802855520
Unscheduled inspection
Start date: 2017-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802678687
Unscheduled inspection
Start date: 2017-10-05, end date: 2017-10-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802733126
Unscheduled inspection
Start date: 2017-10-12, end date: 2017-10-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701898511
Unscheduled inspection
Start date: 2017-08-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701810913
Unscheduled inspection
Start date: 2017-07-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701591929
Unscheduled inspection
Start date: 2017-05-03, end date: 2017-05-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701467136
Unscheduled inspection
Start date: 2017-03-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701379223
Unscheduled inspection
Start date: 2017-02-13, end date: 2017-03-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701333155
Unscheduled inspection
Start date: 2017-01-26, end date: 2017-01-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701317866
Unscheduled inspection
Start date: 2017-01-20, end date: 2017-01-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160701245658
Unscheduled inspection
Start date: 2016-12-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701017795
Unscheduled inspection
Start date: 2016-10-18, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77160700999176
Unscheduled inspection
Start date: 2016-10-07, end date: 2016-10-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: This inspection is carried out in order to eliminate violations specified in the order issued by Mosgosstroynadzor based on the expiration of the deadline for the execution by a legal entity, an individual entrepreneur, of an order issued by the state construction supervision authority to eliminate violations of mandatory requirements. The objectives of this inspection are to prevent identify and suppress violations of technical regulations and project documentation committed by the person being audited. The purpose of this inspection is to verify the elimination of violations specified in the order issued by Mosgosstroynadzor 923916 from 05092016
# 77160700963206
Unscheduled inspection
Start date: 2016-10-05, end date: 2016-10-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: elimination of violations specified in the order issued by Mosgosstroynadzor on the basis of a notification received from the developer the customer or the person carrying out the construction on the elimination of violations. The objectives of this audit are to prevent identify and suppress violations of technical regulations and project documentation committed by the person being audited. The purpose of this audit is to verify the elimination of violations specified in the order issued by Mosgosstroynadzor 860916 dated 01092016
# 77160700084715
Unscheduled inspection
Start date: 2016-08-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160601794750
Unscheduled inspection
Start date: 2016-08-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16150601390228
Unscheduled inspection
Start date: 2015-12-01, end date: 2015-12-28, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere svyazi informacionnyh tehnologii i massovyh kommunikacii po Respublike Tatarstan
Purpose of inspection: verification of compliance with the license terms and mandatory requirements for the provision of communication services in terms of mass distribution of information on the Internet