Found 5 inspections:

# 162101495520
Unscheduled inspection
Start date: 2021-12-24, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 08/31/2021 case No. 16-04-2021/0027. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this review is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162101332888
Unscheduled inspection
Start date: 2021-11-17, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162101333748
Unscheduled inspection
Start date: 2021-11-17, end date: —, duration:
Authority:
Purpose of inspection:


# 162100641981
Unscheduled inspection
Start date: 2021-09-09, end date: —, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 08/31/2021 case No. 16-04-2021/0027. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this review is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100911356
Unscheduled inspection
Start date: 2021-09-28, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.