Found 16 inspections:

# 772005154908
Unscheduled inspection
Start date: 2020-10-02, end date: —, duration:
Authority:
Purpose of inspection:


# 772005203368
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-11-10, duration: 11
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision


# 771904071042
Unscheduled inspection
Start date: 2019-12-05, end date: 2019-12-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 771904167878
Unscheduled inspection
Start date: 2019-12-30, end date: 2020-01-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for energy resources used


# 77190803462345
Unscheduled inspection
Start date: 2019-07-19, end date: 2019-07-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803306540
Unscheduled inspection
Start date: 2018-12-21, end date: 2018-12-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803277017
Unscheduled inspection
Start date: 2018-11-19, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803149391
Unscheduled inspection
Start date: 2018-05-29, end date: 2018-06-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803132408
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 771800077172
Unscheduled inspection
Start date: 2018-02-12, end date: —, duration:
Authority:
Purpose of inspection:


# 77170803018222
Unscheduled inspection
Start date: 2017-12-21, end date: 2017-12-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802902256
Unscheduled inspection
Start date: 2017-11-27, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802844425
Unscheduled inspection
Start date: 2017-11-14, end date: 2017-11-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802164920
Unscheduled inspection
Start date: 2017-09-08, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701128313
Unscheduled inspection
Start date: 2016-11-14, end date: 2016-12-09, duration:
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: kontrol za deyatelnostyu OOO «Signalstroigrupp» svyazannoi s privlecheniem i rashodovaniem denezhnyh sredstv grazhdan dlya stroitelstva zhilogo kompleksa so vstroennymi pomescheniyami obschestvennogo naznacheniya podzemnymi avtostoyankami administrativnym zdaniem i obektami socialnoi infrastruktury po adresu g Moskva SVAO Otradnoe Signalnyi proezd vl 5 kontrol za soblyudeniem polozhenii Federalnogo zakona ot 30122004 214FZ


# 77160601767800
Unscheduled inspection
Start date: 2016-08-02, end date: 2016-08-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 615516 ot 21062016


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.