# 162004458666
Unscheduled inspection
Start date: 2020-07-22, end date: 2020-07-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate from 13072020 7079 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time period established by the regulation from to the Objectives of this Inspections are aimed at preventing, as well as detecting and suppressing violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is the fulfillment of the instructions of state control bodies, supervision bodies of municipal control
# 162004439367
Unscheduled inspection
Start date: 2020-06-25, end date: 2020-06-30, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 26112019 case 121120180125 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004372895
Unscheduled inspection
Start date: 2020-03-26, end date: 2020-04-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 26112019 case 121120180125 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161904163584
Unscheduled inspection
Start date: 2019-12-30, end date: 2020-01-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 26112019 case 121120180125 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161903870457
Unscheduled inspection
Start date: 2019-10-22, end date: 2019-10-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate dated 07102019 9640 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the order from 12092019 1212096401 to 07102019 and the expiration date of the order from 12092019 1212096401, the deadline for which expired on 07102019the objectives of this audit are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentation. Documentationthe subject of this audit is to select the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 161903392323
Unscheduled inspection
Start date: 2019-09-11, end date: 2019-09-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 07122018 case 121120180125the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161902979367
Unscheduled inspection
Start date: 2019-08-21, end date: 2019-08-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 08082019 6999 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the order from 21062019 1212061601 to 26072019 and the expiration of the order from 21062019 1212061601, the deadline for which expired on 26072019the tasks of this audit are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentation. Documentationthe subject of this audit is to select the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 161902803214
Unscheduled inspection
Start date: 2019-06-20, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902667277
Unscheduled inspection
Start date: 2019-04-25, end date: 2019-04-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 07122018 case 121120180125 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902502573
Unscheduled inspection
Start date: 2019-02-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161802306321
Unscheduled inspection
Start date: 2018-12-18, end date: 2018-12-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 07122018 case 121120180125 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts