# 34170802836440
Unscheduled inspection
Start date: 2017-11-07, end date: 2017-11-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya v svyazi s postupleniem 02112017 v Inspekciyu izvescheniya ob ustranenii nedostatkov dopuschennyh pri stroitelstve Obekta s celyu ocenki sootvetstviya deyatelnosti osuschestvlyaemoi na Obekte trebovaniyam gradostroitelnogo zakonodatelstva v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii
# 34170802743799
Unscheduled inspection
Start date: 2017-10-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 34170701661280
Unscheduled inspection
Start date: 2017-05-31, end date: 2017-06-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to comply with the activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection fire safety requirements and sanitary and epidemiological welfare of the population as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation tasks prevention detection and suppression of violations of the legislation of the Russian Federation in including technical regulations and design documentationsubject compliance with mandatory requirements in relation to the compliance of construction works with their results and applied building materials with the requirements of technical regulations of design documentationand the availability of a construction permit and compliance with established requirements for admission to construction work
# 34170701383255
Unscheduled inspection
Start date: 2017-03-01, end date: 2017-03-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to comply with the activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection fire safety requirements and sanitary and epidemiological welfare of the population as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation tasks prevention detection and suppression of violations of the legislation of the Russian Federation in including technical regulations and design documentationsubject compliance with mandatory requirements in relation to the compliance of construction works with their results and applied building materials with the requirements of technical regulations of design documentationand the availability of a construction permit and compliance with established requirements for admission to construction work
# 34160700780133
Unscheduled inspection
Start date: 2016-09-21, end date: 2016-09-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to comply with the activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection fire safety requirements and sanitary and epidemiological welfare of the population as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation tasks prevention detection and suppression of violations of the legislation of the Russian Federation in including technical regulations and design documentationsubject compliance with mandatory requirements in relation to the compliance of construction works with their results and applied building materials with the requirements of technical regulations of design documentationand the availability of a construction permit and compliance with established requirements for admission to construction work