# 442201721607
Unscheduled inspection
Start date: 2022-03-09, end date: 2022-03-11, duration: 3
Authority: Departament stroitelstva, zhilischno-kommunalnogo hozyaistva i toplivno-energeticheskogo kompleksa Kostromskoi oblasti
Purpose of inspection: Target: missing
The tasks of the audit:
There are no verification objectives:
compliance with the requirements of paragraphs 1, 3, 5, Part 3 of Article 54 of the Urban Planning Code of the Russian Federation dated 12/29/2004 No. 190-FZ: - compliance of the work performed and the construction materials and products used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements approved in accordance with the parts 15, 15.2 and 15.3 of Article 48 of this Code of project documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of this Code, are part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code); - requirements established by parts 2 and 3.1 of Article 52 of this Code; - requirements for the procedure for carrying out construction control established by this Code and other regulatory legal acts.
# 442100215128
Unscheduled inspection
Start date: 2021-05-19, end date: 2021-05-21, duration: 3
Authority: Departament stroitelstva, zhilischno-kommunalnogo hozyaistva i toplivno-energeticheskogo kompleksa Kostromskoi oblasti
Purpose of inspection: Cel: proverka soblyudeniya trebovanii zakonodatelstva pri stroitelstve obekta kapitalnogo stroitelstva v sootvetstvii s izvescheniem o srokah zaversheniya rabot, podlezhaschih proverke pri stroitelstve obekta kapitalnogo stroitelstva ot 11.05.2021 № 94, Zadachi: preduprezhdenie, vyyavlenie i presechenie narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, v tom chisle proektnoi dokumentacii, Predmet: sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii), v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;, vypolnenie trebovanii chastei 2 i 3, chasti 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii ot 29.12.2004 № 190-FZ.
# 442005269918
Unscheduled inspection
Start date: 2020-12-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 442005340981
Unscheduled inspection
Start date: 2020-12-15, end date: 2020-12-17, duration: —
Authority: Departament stroitelstva zhilischnokommunalnogo hozyaistva i toplivnoenergeticheskogo kompleksa Kostromskoi oblasti
Purpose of inspection: proverka soblyudeniya trebovanii zakonodatelstva pri stroitelstve obekta kapitalnogo stroitelstva v sootvetstvii s programmoi provedeniya proverok utverzhdennoi ispolnyayuschim obyazannosti direktora departamenta 31072020 g
# 442005206719
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-05, duration: 3
Authority: Departament stroitelstva zhilischnokommunalnogo hozyaistva i toplivnoenergeticheskogo kompleksa Kostromskoi oblasti
Purpose of inspection: compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 and 3 of Part 31 of Article 52 of the Urban Planning Code of the Russian Federation dated 29122004 190FZ