# 612101538417
Unscheduled inspection
Start date: 2021-12-24, end date: —, duration: 4
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraph 10 of the inspection program: Inspection of the completed construction site. Events for MGN, landscaping, landscaping, installation of small molds. Equipment of the capital construction facility with metering devices for used energy resources (subject to the actual completion of all work provided for in the project documentation and notification of completion of construction)
# 612101216191
Unscheduled inspection
Start date: 2021-11-03, end date: —, duration: 10
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This inspection is carried out for the purpose of: fulfilling clause 4 of the inspection program: Installation of monolithic reinforced concrete structures of buildings up to the 14th floor.
The objectives of this audit are: prevention, identification and suppression of violations committed by the developer, the customer, as well as the person carrying out construction on the basis of the contract
with the developer or the customer (hereinafter referred to as the contractor), violations of the legislation on urban planning activities, including project documentation
The subject of this audit is verification of: compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 612101316543
Unscheduled inspection
Start date: 2021-11-23, end date: —, duration: 20
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This inspection is carried out in order to monitor the implementation of clause 9 of the inspection program: Monolithic reinforced concrete structures of the technical floor.
Roofing, wall enclosing structures, brickwork of interior walls, stairs, installation of windows, stained glass windows, doors.
External engineering networks:
-water supply, sewerage, heat supply;
- electricity and gas supply.
The objectives of this audit are: prevention, detection and suppression of violations of urban planning legislation, including technical regulations, and project documentation committed by the developer, the customer, and the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor). The subject of this audit is to verify compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 612101316537
Unscheduled inspection
Start date: 2021-11-23, end date: —, duration: 10
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: This inspection is carried out in order to monitor the implementation of clause 8 of the inspection program: Execution of work in accordance with the letter from the designer of Alfastroyinvest LLC No. 10/06 dated 06/10/2021 based on the results of the review of the protocols of concrete strength of vertical structures.:
1. identification of sections of structures with concrete strength below the design;
2. replacement of sections with concrete strength of B20 and below;
3. treatment with a penetrating compound of the Kalmatron type of wall sections with a strength below the design, but not lower than 22.5. in the case of 01.001.2473
The objectives of this audit are: prevention, detection and suppression of violations of urban planning legislation, including technical regulations, and project documentation committed by the developer, the customer, and the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor). The subject of this audit is to verify compliance with mandatory requirements and (or) requirements established by municipal legal acts
# 612100988433
Unscheduled inspection
Start date: 2021-09-24, end date: —, duration: 5
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: this audit is conducted for the purpose of: verifying the execution of: Order No. 01.001.2684-2 dated 07/21/2021 to 09/21/2021, issued by Stroyservice LLC (TIN 2311201962)
the objectives of this audit are: prevention, identification and suppression of violations committed by the developer, the customer, as well as the person carrying out construction on the basis of the contract
with the developer or the customer (hereinafter referred to as the contractor), violations of the legislation on urban planning activities, including project documentation
The subject of this audit is the verification of: compliance with the regulations of state control (supervision) bodies, municipal control bodies
# 612100310266
Unscheduled inspection
Start date: 2021-06-24, end date: —, duration: —
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection:
# 612100014155
Unscheduled inspection
Start date: 2021-02-15, end date: 2021-02-19, duration: 5
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: checking the execution of the order.
The objectives of this audit are: prevention, detection and suppression of violations of urban planning legislation, including technical regulations, and project documentation, committed by the developer, the customer, and the person carrying out construction on the basis of a contract with the developer or the customer (hereinafter referred to as the contractor) 7. The subject of this audit is to verify: compliance with the regulations of the authorities state control (supervision), municipal control bodies
# 612005295687
Unscheduled inspection
Start date: 2020-12-21, end date: 2021-01-25, duration: 20
Authority: Regionalnaya sluzhba gosudarstvennogo stroitelnogo nadzora Rostovskoi oblasti
Purpose of inspection: Program verification The objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The purpose of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts