# 741902477116
Unscheduled inspection
Start date: 2019-02-05, end date: 2019-02-11, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of ground floor structures and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with project documentation 2 Availability of a construction permit 3 Compliance with the requirements of HR 2 3 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800575423
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-10, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of ground floor structures during the implementation and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 74170802956106
Unscheduled inspection
Start date: 2017-12-20, end date: 2017-12-26, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the installation of ground floor structures during the implementation and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2 The availability of a construction permit3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 74170802729676
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-20, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the foundation during the construction process and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation