# 772004307516
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-03-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for energy resources used
# 772004210965
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-02-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used
# 771902442964
Unscheduled inspection
Start date: 2019-01-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803108025
Unscheduled inspection
Start date: 2018-03-21, end date: 2018-03-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803074202
Unscheduled inspection
Start date: 2018-02-01, end date: 2018-02-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802726040
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-11-13, duration: —
Authority: Ministerstvo Rossiiskoi Federacii po delam grazhdanskoi oborony chrezvychainym situaciyam i likvidacii posledstvii stihiinyh bedstvii MCHS Rossii
Purpose of inspection: Kontrol za ispolneniem predpisaniya GPN 6911 ot 16032017 g ob ustranenie narushenii trebovanii pozharnoi bezopasnosti o provedenii meropriyatii po obespecheniyu pozharnoi bezopasnosti na obektah zaschity i predotvrascheniyu ugrozy vozniknoveniya pozhara
# 77170701386023
Unscheduled inspection
Start date: 2017-02-14, end date: 2017-03-16, duration: —
Authority: Ministerstvo Rossiiskoi Federacii po delam grazhdanskoi oborony chrezvychainym situaciyam i likvidacii posledstvii stihiinyh bedstvii MCHS Rossii
Purpose of inspection: Kontrol za ispolneniem predpisaniya GPN 4811 ot 21032015 g ob ustranenie narushenii trebovanii pozharnoi bezopasnosti o provedenii meropriyatii po obespecheniyu pozharnoi bezopasnosti na obektah zaschity i predotvrascheniyu ugrozy vozniknoveniya pozhara