Found 15 inspections:

# 342004410853
Unscheduled inspection
Start date: 2020-05-20, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:


# 342004267160
Unscheduled inspection
Start date: 2020-02-14, end date: 2020-02-18, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: In order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, the legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, including technical regulations and project documentation. b The purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation. The subject of this audit is compliance with mandatory requirements regarding a compliance of the work performed and the building materials used during the construction reconstruction of a capital construction facility as well as the results of such work with the requirements approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation hereinafter referred to as the Code of Design Documentation, taking into account the amendments made to the design documentation in accordance with Parts 38 and 39 of Article 49 of the Code and or an information model in the event that the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for used energy resources b availability of a construction permit c compliance with the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 341904132907
Unscheduled inspection
Start date: 2019-12-17, end date: 2019-12-19, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in accordance with the inspection program received by a representative of the developer Gazprom Transgaz Volgograd LLC in order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation, legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, including technical regulations and project documentation, the purpose of this inspection is to prevent identify and suppress violations of the legislation Russian Federation, including technical regulations and project documentation


# 341904095611
Unscheduled inspection
Start date: 2019-12-17, end date: 2019-12-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: and this inspection is carried out in accordance with the inspection program received by a representative of the developer Gazprom Transgaz Volgograd LLC in order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation, legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, including technical regulations and design documentationthe purpose of this inspection is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements regarding the compliance of the work and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation hereinafter referred to as the Code of Project Documentation with taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Code and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and equipment requirements of the capital construction facility metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 341903879534
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-10-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: and this inspection is carried out in accordance with the inspection program received by a representative of the developer Gazprom Transgaz Volgograd LLC in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, fire safety requirements and project documentation. The purpose of this inspection is to prevent identify and suppress violations of the legislation of the Russian Federation and project documentation


# 341902550264
Unscheduled inspection
Start date: 2019-03-11, end date: —, duration:
Authority:
Purpose of inspection:


# 341802220558
Unscheduled inspection
Start date: 2018-12-13, end date: 2018-12-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: a this inspection is carried out in accordance with the inspection program received by the representative of the developer Gazprom Transgaz Volgograd LLC in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, fire safety requirements and project documentation b the purpose of this inspection is to prevent identify and suppress violations of the legislation of the Russian Federation and project documentation


# 341801281873
Unscheduled inspection
Start date: 2018-09-25, end date: —, duration:
Authority:
Purpose of inspection:


# 341800527291
Unscheduled inspection
Start date: 2018-07-09, end date: 2018-07-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in connection with the expiration of 22062018 of the deadline for the execution of the order dated 24052018 1705 issued by LLC PKF Derdi on the elimination of violations committed during the construction of the Facility in order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources, including technical regulations and The purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation. The subject of this audit is to comply with the regulations


# 341800366977
Unscheduled inspection
Start date: 2018-05-18, end date: 2018-05-24, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, fire safety requirements, including technical regulations and design documentation, the objective of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and design documentation. The subject of this audit is compliance with mandatory requirements regarding the compliance of construction works with their results and applied b the requirements of the technical regulations of the project documentation b the availability of a building permit c the fulfillment of the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 341800078268
Unscheduled inspection
Start date: 2018-02-14, end date: 2018-02-16, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, including technical regulations and design documentation, the objective of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and design documentation. The subject of this audit is compliance with mandatory requirements regarding the compliance of construction works with their results and the construction materials used materials to the requirements of the technical regulations of the project documentation b the availability of a building permit c the fulfillment of the requirements established by parts 23 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 34170802816857
Unscheduled inspection
Start date: 2017-11-24, end date: —, duration:
Authority:
Purpose of inspection:


# 34170701892895
Unscheduled inspection
Start date: 2017-08-18, end date: 2017-08-24, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, including technical regulations and design documentationthe task of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and design documentationthe subject of this audit is compliance with mandatory requirements in relation to the compliance of construction works, their results and applied building materials with technical requirements regulations of the project documentation, the availability of a construction permit, and the fulfillment of the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 34170701599124
Unscheduled inspection
Start date: 2017-05-12, end date: —, duration:
Authority:
Purpose of inspection:


# 34170701409692
Unscheduled inspection
Start date: 2017-02-14, end date: 2017-02-20, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, including technical regulations and design documentationthe task of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and design documentationthe subject of this audit is compliance with mandatory requirements in relation to the compliance of construction works, their results and applied building materials with technical requirements the regulations of the project documentation, the availability of a construction permit, and the fulfillment of the established requirements for admission to construction work


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.