# 262004478669
Unscheduled inspection
Start date: 2020-08-05, end date: 2020-09-01, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: Objectives of the audit inspection program from 03082020 3222017 objectives of the audit the objectives of this audit are to prevent identify and suppress violations of the law on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out construction. The subject of the audit is compliance with the procedure for conducting construction control, maintaining general and or special work logs, executive documentation, and drawing up certificates of work inspection of structures of network sections engineering and technical support compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources compliance with mandatory requirements and or requirements established by municipal legal acts
# 261903773790
Unscheduled inspection
Start date: 2019-10-03, end date: 2019-10-30, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: The objectives of the inspection are the notice of completion of construction dated 27092019 167420114 the inspection program dated 27032019 26052019 Stage 23 inspection tasks The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer, technical customer, and the person carrying out construction, including technical regulations and project documentation. The subject of the inspection is compliance with other requirements when performing work established by the project documentation, including requirements regarding energy efficiency and requirements regarding the equipment of a capital construction facility with metering devices for used energy resources compliance with mandatory requirements and or requirements established by municipal legal acts
# 261903352676
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-10-04, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: The objectives of the audit are notification of the completion dates of works that are subject to verification from 03092019 153420114 inspection program from 27032019 26052019 Stage 1 inspection tasks The objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer technical customer person carrying out construction, including technical regulations and project documentation subject of verification compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used, compliance with mandatory requirements and or requirements established by municipal legal acts
# 261902568010
Unscheduled inspection
Start date: 2019-03-14, end date: 2019-04-10, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: Objectives of the inspection notification of the start of construction dated 05032019 33330114 objectives of the inspection the objectives of this inspection are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out the construction. The subject of the inspection is compliance with other requirements when performing work established by the project documentation, including requirements regarding energy efficiency and requirements regarding the equipment of the capital construction facility with metering devices for used energy resources, compliance with mandatory requirements and or requirements established by municipal legal acts
# 26160700920636
Unscheduled inspection
Start date: 2016-09-26, end date: —, duration: —
Authority: —
Purpose of inspection: