Found 5 inspections:

# 381904071757
Unscheduled inspection
Start date: 2019-12-11, end date: 2020-01-17, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora Irkutskoi oblasti
Purpose of inspection: verification of the execution of the order, prevention, detection and suppression of violations of the legislation on urban planning activities and project documentation committed by the developer


# 381903694982
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-10-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Irkutskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms


# 14160700866967
Unscheduled inspection
Start date: 2016-09-28, end date: —, duration:
Authority:
Purpose of inspection:


# 14160601788548
Unscheduled inspection
Start date: 2016-08-16, end date: 2016-08-22, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The purpose of the inspection is the tactical elimination of previously identified violations during the construction of a capital construction facility, which were prescribed for elimination by regulation 040811P16 of July 04, 2016. The objectives of the inspection are to prevent identify and suppress violations of urban planning legislation committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, including technical regulations and project documentation


# 14160601788579
Unscheduled inspection
Start date: 2016-08-16, end date: 2016-08-22, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The purpose of the inspection is in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Russian Federation on April 14, 2016, compliance with the mandatory requirements in the field of construction and the applied building materials products of the established procedure for the construction of the capital construction facility inspection tasks prevention detection and suppression of violations committed by the developer technical customer as well as by a person carrying out construction on the basis of a contract with a developer or a technical customer for violations of legislation on urban planning, including technical regulations and design documentationsubject verification of compliance of work performed and construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency requirements and equipment requirements of a capital construction facility availability of a construction permit, compliance with the requirements of Parts 2 and 3 of Article 52 of this Code, availability of a certificate of admission to work on construction and reconstruction that affect the safety of the capital construction facility, including a certificate of admission to work on the organization of a contract of an individual or legal entity


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.