# 772005284476
Unscheduled inspection
Start date: 2020-12-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005235805
Unscheduled inspection
Start date: 2020-11-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005201847
Unscheduled inspection
Start date: 2020-10-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803289525
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803239047
Unscheduled inspection
Start date: 2018-09-26, end date: 2018-09-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803178250
Unscheduled inspection
Start date: 2018-07-10, end date: 2018-07-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used