# 422100024595
Unscheduled inspection
Start date: 2021-02-20, end date: 2021-02-26, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of design documentation and verification of compliance with the requirements of Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422105322898
Unscheduled inspection
Start date: 2021-01-26, end date: 2021-01-29, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of design documentation and verification of compliance with the requirements of Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422005256012
Unscheduled inspection
Start date: 2020-11-24, end date: 2020-11-30, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: s celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta ustroistvo krovli polov zapolnenie okonnyh i dvernyh proemov montazh vnutrennih inzhenernyh kommunikacii vnutrennie otdelochnye raboty a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii zadachei i predmetom nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva
# 422005226460
Unscheduled inspection
Start date: 2020-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422005220935
Unscheduled inspection
Start date: 2020-11-11, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422005190104
Unscheduled inspection
Start date: 2020-10-27, end date: 2020-10-30, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation and to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004533003
Unscheduled inspection
Start date: 2020-08-27, end date: 2020-08-31, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta zadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstvasoblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004484968
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-08-21, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: in order to verify the compliance of the work performed and the building materials used during the construction of the facility, installation of the frame of wall panels and brick partitions roof installation filling of window and door openings installation of external engineering communications exterior finishing works landscaping as well as the results of such work with the requirements of project documentation verification of compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and The subject of this audit is compliance with the legislation of the Russian Federation on urban planning activities during construction
# 422004464495
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-12, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 422004457469
Unscheduled inspection
Start date: 2020-07-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422004440736
Unscheduled inspection
Start date: 2020-06-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422004409785
Unscheduled inspection
Start date: 2020-05-26, end date: 2020-05-29, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 422004406611
Unscheduled inspection
Start date: 2020-05-13, end date: 2020-05-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of verifying the compliance of the work performed and the building materials used during the construction of a capital construction facility with the requirements of the design documentation and in order to verify compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the task and subject of this audit is compliance with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004404864
Unscheduled inspection
Start date: 2020-04-30, end date: 2020-05-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: s celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta zadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004339169
Unscheduled inspection
Start date: 2020-03-19, end date: 2020-03-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 422004251384
Unscheduled inspection
Start date: 2020-02-04, end date: 2020-02-06, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialovzadachei nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstvasoblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422004262926
Unscheduled inspection
Start date: 2020-02-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422004199281
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-01-20, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: the purpose of checking the compliance of the work performed is the installation of stained glass windows, the installation of floors in the operator's room, the finishing work in the operator's room, the facade, the manufacture and installation of a canopy, the canopy cladding, the installation of islands for speakers, the installation of protective screens, the fencing of the unloading area and the laying of paving stones, the power supply network, water supply and sanitation, heating and ventilation, the installation of a control network for technological equipment and applied building materials, the requirements of the design documentation and with the purpose of verifying compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation The task and subject of this audit is to comply with the requirements of the legislation of the Russian Federation on urban planning activities during construction
# 422004213894
Unscheduled inspection
Start date: 2020-01-17, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 421904053057
Unscheduled inspection
Start date: 2019-12-10, end date: 2019-12-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421904001398
Unscheduled inspection
Start date: 2019-11-22, end date: 2019-11-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421904029138
Unscheduled inspection
Start date: 2019-11-27, end date: 2019-11-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903955487
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903876170
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-10-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903905421
Unscheduled inspection
Start date: 2019-10-29, end date: 2019-10-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421903554829
Unscheduled inspection
Start date: 2019-09-20, end date: 2019-09-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902785101
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-06-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902685442
Unscheduled inspection
Start date: 2019-05-27, end date: 2019-05-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902684460
Unscheduled inspection
Start date: 2019-04-26, end date: 2019-05-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902684437
Unscheduled inspection
Start date: 2019-04-26, end date: 2019-05-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902564755
Unscheduled inspection
Start date: 2019-03-21, end date: 2019-03-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902428944
Unscheduled inspection
Start date: 2019-01-29, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 421802336089
Unscheduled inspection
Start date: 2018-12-11, end date: 2018-12-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421802356069
Unscheduled inspection
Start date: 2018-12-13, end date: 2018-12-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421802214628
Unscheduled inspection
Start date: 2018-12-19, end date: 2018-12-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421802138675
Unscheduled inspection
Start date: 2018-11-20, end date: 2018-11-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421802003937
Unscheduled inspection
Start date: 2018-10-29, end date: 2018-11-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421800680868
Unscheduled inspection
Start date: 2018-09-11, end date: 2018-09-17, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421801669151
Unscheduled inspection
Start date: 2018-09-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421800644552
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421800644386
Unscheduled inspection
Start date: 2018-08-29, end date: 2018-09-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421800421848
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-06-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421800465437
Unscheduled inspection
Start date: 2018-06-28, end date: 2018-07-03, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning