# 001801948058
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-19, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the fulfillment by a legal entity of a previously issued instruction on the elimination of identified violations of the mandatory requirements specified in subclause No. 1 of Regulation No. 28052018 4321137114 in subclause No. 15 of 21032018 432128137139064
# 161902923767
Unscheduled inspection
Start date: 2019-06-25, end date: 2019-07-23, duration: —
Authority: SredneVolzhskoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: verification of the accuracy of the information specified in the license application dated 24062019 1602211lits
# 001801948058
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-19, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the fulfillment by a legal entity of a previously issued instruction on the elimination of identified violations of the mandatory requirements specified in subclause No. 1 of Regulation No. 28052018 4321137114 in subclause No. 15 of 21032018 432128137139064
# 161800414834
Unscheduled inspection
Start date: 2018-06-07, end date: 2018-06-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 19012016, case 1151120160002, the prevention and detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation with mandatory requirements or requirements established by municipal legal acts performed during the construction of a capital construction facility
# 161800444511
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-28, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the fulfillment by a legal entity of a previously issued order to eliminate identified violations of the mandatory requirements specified in subclause 618 of the regulation dated 21032018 432128137139064
# 161800366109
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-28, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the fulfillment by a legal entity of a previously issued instruction on the elimination of identified violations of the mandatory requirements specified in subclause 618 of the instruction dated 21032018 432128137139064 compliance with the instructions of state control bodies supervision of municipal control bodies
# 161800247020
Unscheduled inspection
Start date: 2018-04-05, end date: 2018-04-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 19012016, case 1151120160002, the prevention and detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation with mandatory requirements or requirements established by municipal legal acts performed during the construction of a capital construction facility
# 16180803060796
Unscheduled inspection
Start date: 2018-01-19, end date: 2018-01-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of the compliance of the work performed with the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used; determination of the compliance of eliminated violations with the requirements of the technical regulations of the project documentation and other regulatory acts; and drawing up an act on the elimination of violations based on the notice received by the Inspectorate on the elimination of violations during the construction of the reconstruction of the capital construction facility dated 28122017 11040, which was ordered to be eliminated within the time limit set by the order from 08122017 1519070801 to 29122017, the prevention and detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical requirements performed during the construction of the capital construction facility. regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 16170802959456
Unscheduled inspection
Start date: 2017-12-07, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170802545559
Unscheduled inspection
Start date: 2017-09-18, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection:
# 16170802586144
Unscheduled inspection
Start date: 2017-09-19, end date: 2017-10-16, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: protection of the rights and interests of employees
# 16170701817991
Unscheduled inspection
Start date: 2017-07-27, end date: 2017-07-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of compliance of the completed works applied in the process of construction reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used checking the availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 06062017 case 151120160002 prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 16170701817611
Unscheduled inspection
Start date: 2017-07-24, end date: 2017-08-18, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: protection of the rights and interests of employees
# 16170701346976
Unscheduled inspection
Start date: 2017-01-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700894839
Unscheduled inspection
Start date: 2016-10-06, end date: 2016-10-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of a capital construction facility with the construction materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 19052016 case 151120160002 prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts