Found 46 inspections:

# 002004404065
Unscheduled inspection
Start date: 2020-04-03, end date: 2020-04-17, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including the design documentation compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources based on the notice of completion of construction, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of art. 52 of the Urban Planning Code of the Russian Federation


# 001904306809
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-12-06, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including the design documentation compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used based on the program of checks on the availability of a construction permit, compliance with the requirements of parts 2 and 3 of art. 52 of the Urban Planning Code of the Russian Federation


# 001903947040
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-10-29, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of a capital construction facility, based on the notice of completion of construction, SAMARATRANSNEFTEMINAL Oil Refinery LLC Connects the PSP receiving point located at Samara region, Volzhsky district, 23 km east of Nikolaevthe objectives of this inspection are to prevent, identify and prevent violations committed by the developer or customer as well as by a person carrying out construction on the basis of a contract with a developer or customer for violations of legislation on urban planning activities, including project documentation.


# 001903945348
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-10-29, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the completion notice, the SAMAROTRANSNEFTEMINAL Refinery Acceptance Point includes a safety device unit with a TPU unit of the Federal State Institution automation system control room located at 23, Samara Region, Volzhsky District km to the east from Nikolaevthe objectives of this inspection are to prevent identify and suppress violations of the law on urban development activities, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer


# 001902898589
Unscheduled inspection
Start date: 2019-06-18, end date: 2019-07-01, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility "SAMARATRANSNEFTEMINAL Oil refinery" as part of the safety device assembly of the CIC with TPU, the unit of the FSU automation system of the CIC operator room" located at the address Samara region Volzhsky district 23 km east of Nikolaevka on the basis of The objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities, including project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of the requirements of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, the availability of a construction permit, the fulfillment of the requirements of Parts 2 3 and 31 of Art 52 of the Urban Planning Code of the Russian Federation on the basis of a program for conducting inspections of the capital construction facility


# 001902989056
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-04-05, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including the design documentation compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used based on the verification program for the construction permit compliance with the requirements of parts 2 and 3 of Art 52 of the Urban Planning Code of the Russian Federation


# 001902575501
Unscheduled inspection
Start date: 2019-02-13, end date: 2019-02-21, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the fulfillment by SAMARATRANEFTEMINAL LLC of the requirements of the previously issued regulation 078120818306KP dated 17082018, the deadline for which was extended to 12022019 by a letter from the Srednepovolzhsky Administration of Rostechnadzor dated 07112018 011526374 on the elimination of identified violations during the construction of the capital construction facility "Bulk Railway overpass in the Volzhsky district of the Samara region External Railway Transport" located at the address of the Russian Federation Samara region Volzhsky district


# 001902551506
Unscheduled inspection
Start date: 2019-01-22, end date: 2019-02-04, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility "SAMARATRANSNEFTEMINAL Oil refinery" as part of the safety device assembly of the CIC with TPU, the unit of the FSU automation system of the CIC operator room" located at the address Samara region Volzhsky district 23 km east of Nikolaevka on the basis of The objectives of this audit are to prevent identify and suppress violations of the law on urban development activities, including project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of the requirements of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, the availability of a construction permit, the fulfillment of the requirements of Parts 2 3 and 31 of Art 52 of the Urban Planning Code of the Russian Federation on the basis of a program for conducting inspections of the capital construction facility


# 001902988018
Unscheduled inspection
Start date: 2019-01-29, end date: 2019-02-01, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor compliance with the requirements of a previously issued regulation on the elimination of identified violations, verification of the elimination by a legal entity of the identified violations specified in the regulation on the elimination of violations, compliance with the requirements of a previously issued regulation on the elimination of identified violations


# 001801748249
Unscheduled inspection
Start date: 2018-08-29, end date: 2018-09-04, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the fulfillment by SAMARATRANEFTEMINAL LLC of the requirements of the previously issued instruction on the elimination of identified violations dated 28062018 078120618228, the deadline for which expires on 28082018. The objectives of this audit are to verify that the legal entity has eliminated the violations specified in the instruction on the elimination of violations dated 28062018 078120618228, the deadline for which expires on 28082018. The subject of this audit is the fulfillment by the audited entity of the instruction on the elimination of violations from 28062018 078120618228 of the Srednepovolzhsky administration of Rostechnadzor


# 00160701201305
Unscheduled inspection
Start date: 2016-12-05, end date: 2016-12-23, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Samarskoi i Ulyanovskoi oblastyam
Purpose of inspection: control of the fulfillment of the prescription


# 632100308235
Unscheduled inspection
Start date: 2021-06-25, end date: —, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: Verification of compliance with the requirements of labor legislation


# 632100158080
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-23, duration: 10
Authority: Sredne-Povolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation, requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, on the basis of a notice of completion of construction - "Bulk railway overpass in the Volzhsky district of the Samara region. External railway transport", located at the address: Samara region, Volzhsky district; The objectives of this audit are: to verify compliance with the mandatory requirements of legislation on urban development, including project documentation, as well as requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or technical customer


# 632100046309
Unscheduled inspection
Start date: 2021-02-26, end date: —, duration:
Authority: Sredne-Povolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 002004404065
Unscheduled inspection
Start date: 2020-04-03, end date: 2020-04-17, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including the design documentation compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources based on the notice of completion of construction, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of art. 52 of the Urban Planning Code of the Russian Federation


# 631904146217
Unscheduled inspection
Start date: 2019-12-25, end date: 2020-01-29, duration:
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: compliance with labor laws


# 001904306832
Unscheduled inspection
Start date: 2019-12-26, end date: 2019-12-27, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor compliance with the requirements of a previously issued regulation on the elimination of identified violations, verification of the elimination by a legal entity of the identified violations specified in the regulation on the elimination of violations, compliance with the requirements of a previously issued regulation on the elimination of identified violations


# 001904306934
Unscheduled inspection
Start date: 2019-12-26, end date: 2019-12-27, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor compliance with the requirements of a previously issued regulation on the elimination of identified violations, verification of the elimination by a legal entity of the identified violations specified in the regulation on the elimination of violations, compliance with the requirements of a previously issued regulation on the elimination of identified violations


# 001904306809
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-12-06, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including the design documentation compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used based on the program of checks on the availability of a construction permit, compliance with the requirements of parts 2 and 3 of art. 52 of the Urban Planning Code of the Russian Federation


# 001903947040
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-10-29, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of a capital construction facility, based on the notice of completion of construction, SAMARATRANSNEFTEMINAL Oil Refinery LLC Connects the PSP receiving point located at Samara region, Volzhsky district, 23 km east of Nikolaevthe objectives of this inspection are to prevent, identify and prevent violations committed by the developer or customer as well as by a person carrying out construction on the basis of a contract with a developer or customer for violations of legislation on urban planning activities, including project documentation.


# 001903945348
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-10-29, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the completion notice, the SAMAROTRANSNEFTEMINAL Refinery Acceptance Point includes a safety device unit with a TPU unit of the Federal State Institution automation system control room located at 23, Samara Region, Volzhsky District km to the east from Nikolaevthe objectives of this inspection are to prevent identify and suppress violations of the law on urban development activities, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer


# 631902940134
Unscheduled inspection
Start date: 2019-08-08, end date: 2019-08-28, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Samarskoi i Ulyanovskoi oblastyam
Purpose of inspection: monitoring the implementation of the regulation dated 26042019 16


# 631902907488
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-07-31, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 631902878239
Unscheduled inspection
Start date: 2019-07-18, end date: 2019-07-19, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 631902874276
Unscheduled inspection
Start date: 2019-07-24, end date: 2019-07-25, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Implementation of the previously issued regulation 01050815491 dated 25/122018 Notification 2917 dated 09072019


# 001902898589
Unscheduled inspection
Start date: 2019-06-18, end date: 2019-07-01, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility "SAMARATRANSNEFTEMINAL Oil refinery" as part of the safety device assembly of the CIC with TPU, the unit of the FSU automation system of the CIC operator room" located at the address Samara region Volzhsky district 23 km east of Nikolaevka on the basis of The objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities, including project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of the requirements of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, the availability of a construction permit, the fulfillment of the requirements of Parts 2 3 and 31 of Art 52 of the Urban Planning Code of the Russian Federation on the basis of a program for conducting inspections of the capital construction facility


# 631902749446
Unscheduled inspection
Start date: 2019-06-04, end date: 2019-07-02, duration:
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: compliance with labor laws


# 001902723819
Unscheduled inspection
Start date: 2019-04-05, end date: 2019-04-11, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to monitor the fulfillment by SAMARATRANEFTEMINAL LLC of the requirements of the previously issued instruction on the elimination of identified violations dated 04022019 078120219029, the deadline for which expires on 044042019, the objectives of this audit are to verify that the legal entity has eliminated the violations specified in the instruction on the elimination of violations dated 04022019 078120219029, the deadline for which expires on 044042019


# 001902989056
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-04-05, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the design documentation requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including the design documentation compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used based on the verification program for the construction permit compliance with the requirements of parts 2 and 3 of Art 52 of the Urban Planning Code of the Russian Federation


# 001902575501
Unscheduled inspection
Start date: 2019-02-13, end date: 2019-02-21, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the fulfillment by SAMARATRANEFTEMINAL LLC of the requirements of the previously issued regulation 078120818306KP dated 17082018, the deadline for which was extended to 12022019 by a letter from the Srednepovolzhsky Administration of Rostechnadzor dated 07112018 011526374 on the elimination of identified violations during the construction of the capital construction facility "Bulk Railway overpass in the Volzhsky district of the Samara region External Railway Transport" located at the address of the Russian Federation Samara region Volzhsky district


# 001902551506
Unscheduled inspection
Start date: 2019-01-22, end date: 2019-02-04, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of the design documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility "SAMARATRANSNEFTEMINAL Oil refinery" as part of the safety device assembly of the CIC with TPU, the unit of the FSU automation system of the CIC operator room" located at the address Samara region Volzhsky district 23 km east of Nikolaevka on the basis of The objectives of this audit are to prevent identify and suppress violations of the law on urban development activities, including project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of the requirements of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, the availability of a construction permit, the fulfillment of the requirements of Parts 2 3 and 31 of Art 52 of the Urban Planning Code of the Russian Federation on the basis of a program for conducting inspections of the capital construction facility


# 001902988018
Unscheduled inspection
Start date: 2019-01-29, end date: 2019-02-01, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor compliance with the requirements of a previously issued regulation on the elimination of identified violations, verification of the elimination by a legal entity of the identified violations specified in the regulation on the elimination of violations, compliance with the requirements of a previously issued regulation on the elimination of identified violations


# 631802328223
Unscheduled inspection
Start date: 2018-12-24, end date: 2018-12-25, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 631801339425
Unscheduled inspection
Start date: 2018-09-18, end date: —, duration:
Authority:
Purpose of inspection:


# 631801339419
Unscheduled inspection
Start date: 2018-09-18, end date: 2018-09-26, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 001801748249
Unscheduled inspection
Start date: 2018-08-29, end date: 2018-09-04, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the fulfillment by SAMARATRANEFTEMINAL LLC of the requirements of the previously issued instruction on the elimination of identified violations dated 28062018 078120618228, the deadline for which expires on 28082018. The objectives of this audit are to verify that the legal entity has eliminated the violations specified in the instruction on the elimination of violations dated 28062018 078120618228, the deadline for which expires on 28082018. The subject of this audit is the fulfillment by the audited entity of the instruction on the elimination of violations from 28062018 078120618228 of the Srednepovolzhsky administration of Rostechnadzor


# 001800527293
Unscheduled inspection
Start date: 2018-06-19, end date: 2018-06-22, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the fulfillment by SAMARATRANSNEFTEMINAL LLC of the requirements of the previously issued regulation on the elimination of identified violations dated 16042018 078120418126KP, the deadline for which expires on 18062018. The objectives of this audit are to verify that the legal entity has eliminated the violations specified in the regulation on the elimination of violations dated 16042018 078120418126KP, the deadline for which expires on 18062018. The subject of this audit is the fulfillment by the audited entity of the regulation on the elimination of violations dated 16042018 078120418126KP of the Srednepovolzhsky administration of Rostechnadzor


# 001800526896
Unscheduled inspection
Start date: 2018-06-20, end date: 2018-06-28, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility, SAMARATRANSNEFTEMINAL Oil Refinery LLC Connected the PSP receiving point located at Samara region, Volzhsky district, 23 km east of Nikolaevka, based on the program for conducting inspections of the capital construction facility, the objectives of this The purpose of the audit is to prevent identify and suppress violations of urban planning legislation, including technical regulations of project documentation, committed by the developer, the customer, as well as by persons carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is to verify the compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of a construction permit, the fulfillment of the requirements of parts 2 and 3 of Art 52 of the Urban Planning Code of the Russian Federation on the basis of a program for conducting inspections of the capital construction facility


# 001800392491
Unscheduled inspection
Start date: 2018-04-10, end date: 2018-04-16, duration:
Authority: SrednePovolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to monitor the fulfillment by SAMARATRANEFTEMINAL LLC of the requirements of the previously issued instruction on the elimination of identified violations dated 06022018 078120218024, the deadline for which expires on 049042018. The objectives of this audit are to verify that the legal entity has eliminated the violations specified in the instruction on the elimination of violations dated 06022018 078120218024, the deadline for which expires on 049042018. The subject of this audit is the Fulfillment by the audited entity of the instruction on the elimination of violations from 06022018 078120218024 of the Srednepovolzhsky administration of Rostechnadzor


# 63170802714482
Unscheduled inspection
Start date: 2017-10-18, end date: 2017-10-23, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 25032015 notification dated 02102017 4105 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used


# 63170802714432
Unscheduled inspection
Start date: 2017-10-18, end date: —, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:


# 00170701611650
Unscheduled inspection
Start date: 2017-04-26, end date: 2017-06-09, duration:
Authority: Federalnaya sluzhba po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the instruction of the Deputy Chairman of the Government of the Russian Federation AV Dvorkovich, paragraph 5 of the minutes of the meeting with the Deputy Chairman of the Government of the Russian Federation AV Dvorkovich dated May 26, 2016 ADP274pr


# 63170701409226
Unscheduled inspection
Start date: 2017-03-01, end date: 2017-03-02, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 19012017 notification dated 17022017 567 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used


# 63160701224550
Unscheduled inspection
Start date: 2016-12-13, end date: 2016-12-14, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 21092016 notification dated 05/122016 6776 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used


# 00160701201305
Unscheduled inspection
Start date: 2016-12-05, end date: 2016-12-23, duration:
Authority: Mezhregionalnoe upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Samarskoi i Ulyanovskoi oblastyam
Purpose of inspection: control of the fulfillment of the prescription


# 63160701158522
Unscheduled inspection
Start date: 2016-12-01, end date: 2016-12-02, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.