Found 7 inspections:

# 632100269630
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Samarskoi oblasti
Purpose of inspection:


# 632004448819
Unscheduled inspection
Start date: 2020-07-17, end date: 2020-08-13, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Samarskoi oblasti
Purpose of inspection: The audit is carried out with the aim of implementing federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms. The objectives of this audit are to ensure compliance with and protection of labor rights and freedoms of citizens, including the right to safe working conditions. The subject of this audit is compliance with the requirements or requirements of labor legislation and other regulatory legal acts containing labor law norms


# 632004410523
Unscheduled inspection
Start date: 2020-05-19, end date: 2020-05-29, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 632004407146
Unscheduled inspection
Start date: 2020-05-13, end date: 2020-05-22, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 632004389048
Unscheduled inspection
Start date: 2020-04-02, end date: —, duration:
Authority:
Purpose of inspection:


# 632004380246
Unscheduled inspection
Start date: 2020-03-27, end date: 2020-04-15, duration:
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 632004282608
Unscheduled inspection
Start date: 2020-03-10, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.