# 00170802290948
Unscheduled inspection
Start date: 2017-09-18, end date: —, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 722100330804
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: 15
Authority: Severo-Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to: comply with clause 1.1. of Order No. 222 of the Federal Service for Environmental, Technological and Nuclear Supervision dated June 18, 2021 "On Monitoring the preparation of Electric Power and Heat Supply Facilities for operation in the Autumn-winter period of 2021-2022" pursuant to the instruction of the Government of the Russian Federation dated June 11, 2021 No. AN-P51-7582;
The objectives of this audit are: prevention, detection and suppression of violations of mandatory requirements established by regulatory legal acts.
7. The subject of this audit is (please note):
compliance with mandatory requirements or requirements established by legal acts.
# 00170802290948
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-22, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this audit is being conducted in order to verify the implementation of paragraphs 16 of Regulation No. 10082017 577425P issued by the North Ural Rostechnadzor Department. The objectives of this audit are to verify the elimination of violations identified by the North Ural Rostechnadzor Department during an audit of the Limited Liability Company EltransThe subject of this audit is the fulfillment of the instructions of the state control bodies of supervision of municipal control bodies
# 00170701813178
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-08-11, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is conducted in order to verify the progress of the preparation of electricity and heat supply organizations for work in the autumn and winter period of 2017-2018 Order of the Federal Service for Environmental Technological and Nuclear Supervision dated 10072017 256 The objectives of this inspection are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The purpose of this inspection is to note the necessary compliance with mandatory requirements or requirements established by legal acts acts