# 771903575678
Unscheduled inspection
Start date: 2019-09-11, end date: 2019-09-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with checking the fulfillment of the prescriptionthe tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activity by the audited person. The purpose of the audit is to verify the elimination of violations specified in the prescription issued by Mosgosstroynadzor


# 77190803453363
Unscheduled inspection
Start date: 2019-07-11, end date: 2019-07-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803444900
Unscheduled inspection
Start date: 2019-07-08, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803432951
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, fulfillment by the person carrying out the construction requirements of part 3 of Article 52 of the Urban Planning Code


# 77190803412771
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-05-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code is the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources


# 77190803412772
Unscheduled inspection
Start date: 2019-05-20, end date: 2019-05-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803384710
Unscheduled inspection
Start date: 2019-04-12, end date: 2019-04-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803367775
Unscheduled inspection
Start date: 2019-03-12, end date: —, duration:
Authority:
Purpose of inspection: