# 001902869823
Unscheduled inspection
Start date: 2019-07-03, end date: 2019-07-04, duration: —
Authority: Federalnaya sluzhba po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka
Purpose of inspection: The purpose of the audit is to assess the compliance of information with licensing requirements The task of the audit is to identify suppress and prevent violations of legislation in the field of ensuring sanitary and epidemiological well-being of a person The subject of the audit is compliance with mandatory requirements established by Federal Law No. 99 FZ of May 4, 2011 and Decree of the Government of the Russian Federation dated April 2, 2012 278
# 502004444270
Unscheduled inspection
Start date: 2020-07-03, end date: 2020-07-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms
# 001902869823
Unscheduled inspection
Start date: 2019-07-03, end date: 2019-07-04, duration: —
Authority: Federalnaya sluzhba po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka
Purpose of inspection: The purpose of the audit is to assess the compliance of information with licensing requirements The task of the audit is to identify suppress and prevent violations of legislation in the field of ensuring sanitary and epidemiological well-being of a person The subject of the audit is compliance with mandatory requirements established by Federal Law No. 99 FZ of May 4, 2011 and Decree of the Government of the Russian Federation dated April 2, 2012 278
# 761902557403
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-03-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: the audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements
# 761902557377
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-03-11, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: the audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements
# 761802344540
Unscheduled inspection
Start date: 2018-12-26, end date: 2018-12-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: the audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements
# 761802149365
Unscheduled inspection
Start date: 2018-11-27, end date: 2018-11-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out with the aim of, on the basis of the notice of the beginning of construction of the capital construction facility dated 01112018 bx 1573, the objectives of this audit are to determine the fulfillment of the requirements of part 5 of Article 52 of the Urban Planning Code of the Russian Federation when carrying out work on the construction of the capital construction facility, the subject of this audit is compliance with mandatory requirements
# 761802149400
Unscheduled inspection
Start date: 2018-11-27, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: